Estimated disbursements (<strong>Bank</strong> FY/US$m)<br />
FY 2010 2011 2012 2013 2014 2015<br />
Annual 3 19 74 130 127 77<br />
Cumulative 3 22 96 226 353 430<br />
Project implementation period: Start January 31, 2010 End: June 15, 2015<br />
Expected effectiveness date: September 15, 2010<br />
Expected closing date: June 15, 2015<br />
Does the project depart from the CAS in content or other significant respects<br />
Ref. PAD I.C.<br />
Does the project require any exceptions from <strong>Bank</strong> policies<br />
Ref. PAD IV.G.<br />
Have these been approved by <strong>Bank</strong> management<br />
Is approval for any policy exception sought from the Board<br />
Does the project include any critical risks rated “substantial” or “high”<br />
Ref. PAD III.E.<br />
Does the project meet the Regional criteria for readiness for implementation<br />
Ref. PAD IV.G.<br />
[ ]Yes [X ] No<br />
[ ]Yes [X] No<br />
[ ]Yes [ ] No<br />
[ ]Yes [X] No<br />
[ ]Yes [X] No<br />
[ X ]Yes [ ] No<br />
Project development objective Ref. PAD II.C., Technical Annex 3<br />
To improve the passenger carrying capacity, operational efficiency, level of comfort of, and the<br />
institutional capacity of entities involved in, the suburban rail system of <strong>Mumbai</strong> Metropolitan<br />
area.<br />
Project description Ref. PAD II.D., Technical Annex 4<br />
Component 1: Rolling stock fleet increase with procurement of 864 EMU cars.<br />
Component 2: Conversion of electric traction system from 1500V DC to 25kV AC on the<br />
Central <strong>Railway</strong>, with signal and telecom system improvements.<br />
Component 3: Maintenance facilities and stabling lines to accommodate the additional trains.<br />
Component 4: Capacity Strengthening and Technical assistance.<br />
Which safeguard policies are triggered, if any Ref. PAD IV.F., Technical Annex 10<br />
Environmental Assessment (OP/BP 4.01)<br />
Involuntary Resettlement (OP/BP 4.12)<br />
Significant, non-standard conditions, if any, for:<br />
Ref. PAD III.F.<br />
Loan/credit effectiveness:<br />
The Additional Conditions of Effectiveness consist of the following: the SFA and the MOU with<br />
the ICF have been executed.<br />
vi