10.04.2015 Views

ASPIRE Winter 10 - Aspire - The Concrete Bridge Magazine

ASPIRE Winter 10 - Aspire - The Concrete Bridge Magazine

ASPIRE Winter 10 - Aspire - The Concrete Bridge Magazine

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>The</strong> 50-ft simple-span Pi girders are supported<br />

on plain neoprene bearing pads.<br />

Due to the high costs of upgrading and<br />

modifying the forms, the sole fabricator<br />

interested in casting the modified Pi<br />

sections delivered a bid that was too high<br />

for the budget. FHWA officials at TFHRC<br />

suggested that further revisions be made<br />

to the first-generation section and new<br />

forms be created for a second-generation<br />

Pi girder. <strong>The</strong> FHWA agreed to fund the<br />

forms and purchase two test beams for<br />

evaluation. <strong>The</strong> three production beams<br />

would be purchased at the same time<br />

to reduce setup and casting costs for all<br />

of the beams. In addition, the revised<br />

section would be available for use on<br />

future projects by other state agencies.<br />

This approach was taken, leading to four<br />

key revisions being made to the firstgeneration<br />

section:<br />

1. Two types of fillets, 5 in. and 8 in.<br />

deep, were added at the web-todeck<br />

connection to improve concrete<br />

flow during placement and to stiffen<br />

the slab section.<br />

2. <strong>The</strong> interior deck thickness between<br />

the webs was increased to 4 1 /8 in. to<br />

reduce service load stresses.<br />

3. <strong>The</strong> web spacing was reduced by<br />

4 in. to provide a more balanced<br />

spacing of the webs for the threebeam<br />

cross section and to reduce<br />

service load stresses.<br />

4. <strong>The</strong> post-tensioning was removed<br />

from the deck. Due to the lack of test<br />

data on the revised section, No. 5<br />

reinforcing bars at 1-ft centers were<br />

included in the deck.<br />

Two 25-ft-long test beams were cast first,<br />

followed by three 51-ft-long production<br />

beams. <strong>The</strong> three bridge beams were 8<br />

ft 4 in. wide and 2 ft 9 in. deep with two<br />

tapered webs about 3 in. thick spaced at<br />

4 ft 5 in. Deck thickness was a constant<br />

4 1 /8 in. between the webs and a tapered<br />

thickness outside the webs from 6 7 /8 in. to<br />

5 1 /4 in. at the edge of the slab. Flanges at<br />

the bottom of the beam webs were 7 in.<br />

deep by 1 ft wide. Each flange contained<br />

nine 0.6-in.-diameter strands tensioned to<br />

72.6% of ultimate. Total concrete quantity<br />

was 11.3 yd 3 of UHPC per unit.<br />

Ready-Mixed <strong>Concrete</strong><br />

Trucks Used<br />

Typically, high-speed pan mixers are used<br />

because of the large amount of time<br />

and energy needed to thoroughly mix<br />

the concrete. In this case, ready-mixed<br />

concrete trucks were used for mixing the<br />

required 21,500 psi design compressive<br />

strength. As the material’s performance<br />

is affected by the alignment of the steel<br />

fibers, a horizontal bucket almost as wide<br />

as the form was fabricated to place the<br />

material so it would flow freely along the<br />

form and properly align the fibers.<br />

<strong>The</strong> beams were cured in two stages.<br />

<strong>The</strong> first stage involved curing at ambient<br />

temperatures, although steam curing up to<br />

115 °F could be used in a similar manner to<br />

curing precast, prestressed concrete beams.<br />

<strong>The</strong> Pi girders were covered with plastic and<br />

kept at ambient temperatures until matchcured<br />

cylinders indicated a compressive<br />

strength of 5<strong>10</strong>0 psi had been achieved.<br />

<strong>The</strong>n the forms were opened but left in<br />

place to allow for shrinkage of the section.<br />

Curing at ambient temperatures continued<br />

until the compressive strength of matchcured<br />

cylinders reached 14,500 psi. <strong>The</strong><br />

forms then were removed and the strands<br />

were detensioned.<br />

<strong>The</strong> second curing stage began with<br />

thermal treatment applied to the UHPC<br />

beams with moisture present. <strong>The</strong> goal<br />

was to achieve a temperature of about<br />

190 °F along with relative humidity of at<br />

least 95% for at least 48 hours. <strong>The</strong>rmal<br />

treatments have been shown to enhance<br />

not only the members’ strength but<br />

their durability as well. <strong>The</strong> beams were<br />

wrapped with insulating tarps, and steam<br />

was injected underneath the girders. <strong>The</strong><br />

temperature was increased gradually over<br />

a period of approximately 6 hours. Once<br />

the second curing period was completed,<br />

the curing temperature was decreased<br />

gradually over a period of approximately<br />

6 hours.<br />

<strong>The</strong> beams were fabricated in September<br />

2008, while the contractor began<br />

mobilization, grading, and substructure<br />

work. <strong>The</strong> beams were erected in mid-<br />

October, and the concrete for the end<br />

spans was placed a few weeks later. <strong>The</strong><br />

project was completed in November,<br />

requiring 52 days from start to finish.<br />

Waffle Slab Project<br />

Work with UHPC continues, with a third<br />

bridge project now under development<br />

with Coreslab Structures (Omaha) in<br />

Bellevue, Neb., for use in Wapello<br />

County, Iowa. This project will use the<br />

UHPC mix in a precast concrete deck<br />

on a single-span, prestressed concrete<br />

beam bridge. To optimize the material,<br />

the deck panels will be cast with a waffle<br />

shape. Component casting is scheduled<br />

to begin in the winter of 2009-20<strong>10</strong>,<br />

with construction to take place in the<br />

summer of 20<strong>10</strong>.<br />

By using UHPC in bulb-tee beams, the<br />

optimized pi girder, and a waffle-shaped<br />

deck panel, the project team will expand<br />

the knowledge base and facilitate the<br />

wider use of advanced cementitious<br />

materials to solve specific transportation<br />

challenges.<br />

____________<br />

Brian Keierleber, is county engineer for<br />

Buchanan County, Independence, Iowa;<br />

Dean Bierwagen, and Ahmad Abu-<br />

Hawash, are with the Office of <strong>Bridge</strong>s<br />

& Structures of the Iowa DOT in Ames,<br />

Iowa; and Terry Wipf, is director of the<br />

<strong>Bridge</strong> Engineering Center at Iowa State<br />

University in Ames, Iowa.<br />

For more information on this or other<br />

projects, visit www.aspirebridge.org.<br />

26 | <strong>ASPIRE</strong>, <strong>Winter</strong> 20<strong>10</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!