ASPIRE Winter 10 - Aspire - The Concrete Bridge Magazine
ASPIRE Winter 10 - Aspire - The Concrete Bridge Magazine
ASPIRE Winter 10 - Aspire - The Concrete Bridge Magazine
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>The</strong> 50-ft simple-span Pi girders are supported<br />
on plain neoprene bearing pads.<br />
Due to the high costs of upgrading and<br />
modifying the forms, the sole fabricator<br />
interested in casting the modified Pi<br />
sections delivered a bid that was too high<br />
for the budget. FHWA officials at TFHRC<br />
suggested that further revisions be made<br />
to the first-generation section and new<br />
forms be created for a second-generation<br />
Pi girder. <strong>The</strong> FHWA agreed to fund the<br />
forms and purchase two test beams for<br />
evaluation. <strong>The</strong> three production beams<br />
would be purchased at the same time<br />
to reduce setup and casting costs for all<br />
of the beams. In addition, the revised<br />
section would be available for use on<br />
future projects by other state agencies.<br />
This approach was taken, leading to four<br />
key revisions being made to the firstgeneration<br />
section:<br />
1. Two types of fillets, 5 in. and 8 in.<br />
deep, were added at the web-todeck<br />
connection to improve concrete<br />
flow during placement and to stiffen<br />
the slab section.<br />
2. <strong>The</strong> interior deck thickness between<br />
the webs was increased to 4 1 /8 in. to<br />
reduce service load stresses.<br />
3. <strong>The</strong> web spacing was reduced by<br />
4 in. to provide a more balanced<br />
spacing of the webs for the threebeam<br />
cross section and to reduce<br />
service load stresses.<br />
4. <strong>The</strong> post-tensioning was removed<br />
from the deck. Due to the lack of test<br />
data on the revised section, No. 5<br />
reinforcing bars at 1-ft centers were<br />
included in the deck.<br />
Two 25-ft-long test beams were cast first,<br />
followed by three 51-ft-long production<br />
beams. <strong>The</strong> three bridge beams were 8<br />
ft 4 in. wide and 2 ft 9 in. deep with two<br />
tapered webs about 3 in. thick spaced at<br />
4 ft 5 in. Deck thickness was a constant<br />
4 1 /8 in. between the webs and a tapered<br />
thickness outside the webs from 6 7 /8 in. to<br />
5 1 /4 in. at the edge of the slab. Flanges at<br />
the bottom of the beam webs were 7 in.<br />
deep by 1 ft wide. Each flange contained<br />
nine 0.6-in.-diameter strands tensioned to<br />
72.6% of ultimate. Total concrete quantity<br />
was 11.3 yd 3 of UHPC per unit.<br />
Ready-Mixed <strong>Concrete</strong><br />
Trucks Used<br />
Typically, high-speed pan mixers are used<br />
because of the large amount of time<br />
and energy needed to thoroughly mix<br />
the concrete. In this case, ready-mixed<br />
concrete trucks were used for mixing the<br />
required 21,500 psi design compressive<br />
strength. As the material’s performance<br />
is affected by the alignment of the steel<br />
fibers, a horizontal bucket almost as wide<br />
as the form was fabricated to place the<br />
material so it would flow freely along the<br />
form and properly align the fibers.<br />
<strong>The</strong> beams were cured in two stages.<br />
<strong>The</strong> first stage involved curing at ambient<br />
temperatures, although steam curing up to<br />
115 °F could be used in a similar manner to<br />
curing precast, prestressed concrete beams.<br />
<strong>The</strong> Pi girders were covered with plastic and<br />
kept at ambient temperatures until matchcured<br />
cylinders indicated a compressive<br />
strength of 5<strong>10</strong>0 psi had been achieved.<br />
<strong>The</strong>n the forms were opened but left in<br />
place to allow for shrinkage of the section.<br />
Curing at ambient temperatures continued<br />
until the compressive strength of matchcured<br />
cylinders reached 14,500 psi. <strong>The</strong><br />
forms then were removed and the strands<br />
were detensioned.<br />
<strong>The</strong> second curing stage began with<br />
thermal treatment applied to the UHPC<br />
beams with moisture present. <strong>The</strong> goal<br />
was to achieve a temperature of about<br />
190 °F along with relative humidity of at<br />
least 95% for at least 48 hours. <strong>The</strong>rmal<br />
treatments have been shown to enhance<br />
not only the members’ strength but<br />
their durability as well. <strong>The</strong> beams were<br />
wrapped with insulating tarps, and steam<br />
was injected underneath the girders. <strong>The</strong><br />
temperature was increased gradually over<br />
a period of approximately 6 hours. Once<br />
the second curing period was completed,<br />
the curing temperature was decreased<br />
gradually over a period of approximately<br />
6 hours.<br />
<strong>The</strong> beams were fabricated in September<br />
2008, while the contractor began<br />
mobilization, grading, and substructure<br />
work. <strong>The</strong> beams were erected in mid-<br />
October, and the concrete for the end<br />
spans was placed a few weeks later. <strong>The</strong><br />
project was completed in November,<br />
requiring 52 days from start to finish.<br />
Waffle Slab Project<br />
Work with UHPC continues, with a third<br />
bridge project now under development<br />
with Coreslab Structures (Omaha) in<br />
Bellevue, Neb., for use in Wapello<br />
County, Iowa. This project will use the<br />
UHPC mix in a precast concrete deck<br />
on a single-span, prestressed concrete<br />
beam bridge. To optimize the material,<br />
the deck panels will be cast with a waffle<br />
shape. Component casting is scheduled<br />
to begin in the winter of 2009-20<strong>10</strong>,<br />
with construction to take place in the<br />
summer of 20<strong>10</strong>.<br />
By using UHPC in bulb-tee beams, the<br />
optimized pi girder, and a waffle-shaped<br />
deck panel, the project team will expand<br />
the knowledge base and facilitate the<br />
wider use of advanced cementitious<br />
materials to solve specific transportation<br />
challenges.<br />
____________<br />
Brian Keierleber, is county engineer for<br />
Buchanan County, Independence, Iowa;<br />
Dean Bierwagen, and Ahmad Abu-<br />
Hawash, are with the Office of <strong>Bridge</strong>s<br />
& Structures of the Iowa DOT in Ames,<br />
Iowa; and Terry Wipf, is director of the<br />
<strong>Bridge</strong> Engineering Center at Iowa State<br />
University in Ames, Iowa.<br />
For more information on this or other<br />
projects, visit www.aspirebridge.org.<br />
26 | <strong>ASPIRE</strong>, <strong>Winter</strong> 20<strong>10</strong>