Mine to Market November-December 2012 - Mount Isa Mines
Mine to Market November-December 2012 - Mount Isa Mines
Mine to Market November-December 2012 - Mount Isa Mines
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Main decline<br />
reaches final depth<br />
A Jumbo Opera<strong>to</strong>r drills the face of<br />
the underground decline at EHM<br />
Last month, the Ernest Henry Mining (EHM) underground<br />
team achieved a significant miles<strong>to</strong>ne, completing the<br />
development of the main underground decline.<br />
After making the first cut for the main decline on<br />
20 February 2008, the team overcame numerous challenges<br />
during the development, including managing heat, ventilation<br />
and water issues <strong>to</strong> achieve this impressive result. Now complete,<br />
the decline is approximately 5 kilometres long and reaches a<br />
depth almost 1 kilometre below the surface.<br />
Adam Beswick, EHM Underground Manager, says the<br />
outcome is a credit <strong>to</strong> the efforts of all personnel involved<br />
in the project.<br />
“The team has done a fantastic job <strong>to</strong> get this far and it<br />
means we are on track <strong>to</strong> reach other project miles<strong>to</strong>nes in<br />
the near future,” Adam says.<br />
“We are now mining <strong>to</strong>wards the crusher chamber, and we<br />
hope <strong>to</strong> commence construction of the crusher by the end of<br />
the first quarter next year.<br />
“We are also working our way <strong>to</strong>ward the bot<strong>to</strong>m of the<br />
shaft, where we will begin construction of the loading station<br />
in 2013.”<br />
Underground shaft<br />
and headframe<br />
construction<br />
continues at EHM<br />
Works continue at Ernest Henry Mining (EHM)<br />
<strong>to</strong> progress the shaft sink and headframe<br />
construction, two major components of<br />
EMH’s underground development project.<br />
Once complete, the shaft will be 936 metres deep and<br />
transport six million <strong>to</strong>nnes of ore <strong>to</strong> the surface every year.<br />
Jo Louw, Manager Project Construction, says the project<br />
is coming along in line with schedule.<br />
“We are now in the third phase and will complete the<br />
remainder of the headframe construction concurrently with<br />
the shaft sinking by the end of <strong>December</strong> <strong>2012</strong>,” Jo says.<br />
As work on the headframe continues directly above, shaft<br />
sinking activities have been underway beneath the surface.<br />
The main sink activities kicked off in May <strong>2012</strong> and a dedicated<br />
crew of 70 have worked around the clock <strong>to</strong> sink the shaft more<br />
than 200 metres below the surface <strong>to</strong> date.<br />
The shaft sink is expected <strong>to</strong> be complete by the end<br />
of 2013. It will then take another two months <strong>to</strong> install the<br />
shaft sink steel work and loading equipment.<br />
Designed primarily for ore haulage, the shaft will<br />
also provide man riding for emergency egress from<br />
the underground.<br />
The headframe winder beam is installed at EHM<br />
mine <strong>to</strong> market<br />
7