27.04.2015 Views

Mine to Market November-December 2012 - Mount Isa Mines

Mine to Market November-December 2012 - Mount Isa Mines

Mine to Market November-December 2012 - Mount Isa Mines

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Main decline<br />

reaches final depth<br />

A Jumbo Opera<strong>to</strong>r drills the face of<br />

the underground decline at EHM<br />

Last month, the Ernest Henry Mining (EHM) underground<br />

team achieved a significant miles<strong>to</strong>ne, completing the<br />

development of the main underground decline.<br />

After making the first cut for the main decline on<br />

20 February 2008, the team overcame numerous challenges<br />

during the development, including managing heat, ventilation<br />

and water issues <strong>to</strong> achieve this impressive result. Now complete,<br />

the decline is approximately 5 kilometres long and reaches a<br />

depth almost 1 kilometre below the surface.<br />

Adam Beswick, EHM Underground Manager, says the<br />

outcome is a credit <strong>to</strong> the efforts of all personnel involved<br />

in the project.<br />

“The team has done a fantastic job <strong>to</strong> get this far and it<br />

means we are on track <strong>to</strong> reach other project miles<strong>to</strong>nes in<br />

the near future,” Adam says.<br />

“We are now mining <strong>to</strong>wards the crusher chamber, and we<br />

hope <strong>to</strong> commence construction of the crusher by the end of<br />

the first quarter next year.<br />

“We are also working our way <strong>to</strong>ward the bot<strong>to</strong>m of the<br />

shaft, where we will begin construction of the loading station<br />

in 2013.”<br />

Underground shaft<br />

and headframe<br />

construction<br />

continues at EHM<br />

Works continue at Ernest Henry Mining (EHM)<br />

<strong>to</strong> progress the shaft sink and headframe<br />

construction, two major components of<br />

EMH’s underground development project.<br />

Once complete, the shaft will be 936 metres deep and<br />

transport six million <strong>to</strong>nnes of ore <strong>to</strong> the surface every year.<br />

Jo Louw, Manager Project Construction, says the project<br />

is coming along in line with schedule.<br />

“We are now in the third phase and will complete the<br />

remainder of the headframe construction concurrently with<br />

the shaft sinking by the end of <strong>December</strong> <strong>2012</strong>,” Jo says.<br />

As work on the headframe continues directly above, shaft<br />

sinking activities have been underway beneath the surface.<br />

The main sink activities kicked off in May <strong>2012</strong> and a dedicated<br />

crew of 70 have worked around the clock <strong>to</strong> sink the shaft more<br />

than 200 metres below the surface <strong>to</strong> date.<br />

The shaft sink is expected <strong>to</strong> be complete by the end<br />

of 2013. It will then take another two months <strong>to</strong> install the<br />

shaft sink steel work and loading equipment.<br />

Designed primarily for ore haulage, the shaft will<br />

also provide man riding for emergency egress from<br />

the underground.<br />

The headframe winder beam is installed at EHM<br />

mine <strong>to</strong> market<br />

7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!