19.11.2012 Views

Saiccor - The First 50 Years 5.8 MB - Sappi

Saiccor - The First 50 Years 5.8 MB - Sappi

Saiccor - The First 50 Years 5.8 MB - Sappi

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> Mackenzie Period (1987–1989)<br />

pm my wife Yvonne, clutching a bottle of champagne<br />

(much to Franco Scarpa’s protestations, as he thought<br />

there were much better uses for a bottle of champagne),<br />

clambered into the pipe trench to launch the pipeline,<br />

named ‘Ted’s Flute’�<br />

A temporary jetty was specially constructed for the<br />

‘pulling’ of the pipe� Contractors Smit Tak, under Cor<br />

Vermeer, were a very professional outfit, steadily pulling<br />

the pipe 3 km out to sea from 3�30 pm on 12 to 20<br />

September, without any major problem� <strong>The</strong> landline<br />

was then laid and the new effluent pipeline was<br />

commissioned on 20 November 1987� This was a very<br />

successful project, coming in on time and within the<br />

R30 million budget, and complaints about effluent<br />

ceased until the Mkomazi plant was commissioned in<br />

1995�<br />

About a week after the laying of the new pipeline,<br />

420 mm of rain fell in the Mkomazi catchment area,<br />

most of it between 25 and 29 September� <strong>The</strong> river level<br />

started rising steadily� By the morning of the 28th the<br />

level was looking dangerous and cooking was stopped�<br />

By 3�30 pm the rest of the factory was stopped� At 6 pm<br />

the water intake was abandoned as water was starting<br />

to run across the operating floor, which was normally<br />

some 8 m above the river level� <strong>The</strong> river flow reached a<br />

peak of 7 000 cumecs (2<strong>50</strong> 000 cusecs), coming to within<br />

half a metre of the top of the berm on the west side of the factory,<br />

and dangerously close to flowing into the site at the woodyard�<br />

<strong>The</strong> flood had wreaked havoc� <strong>The</strong> open effluent channel from the<br />

factory to the pumphouse (3,5 km) was filled with mud� <strong>The</strong> plastic<br />

lining in the channel had been ripped for 1 km, 1,1 km of rail line<br />

ballast had been damaged, the overhead power line to the effluent<br />

pumphouse was down for 1,5 km, and the walkway to the intake<br />

pumps and the sheet piling were destroyed� <strong>The</strong> new effluent pipeline<br />

LEFT, the road bridge to Magabeni at the time of the flood and, RIGHT,<br />

under normal conditions<br />

133<br />

<strong>The</strong> temporary jetty constructed for the ‘pulling’ of<br />

the pipe by contractors Smit Tak<br />

<strong>The</strong> plaque commemorating the launch of the effluent<br />

pipeline, ‘Ted’s Flute’, on 12 September 1987<br />

TOP, the factory at the time of the<br />

flood (downstream from the<br />

bridge) and, BOTTOM, under<br />

normal conditions

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!