12.07.2015 Views

eLegalix - Allahabad High Court Judgment Information System ...

eLegalix - Allahabad High Court Judgment Information System ...

eLegalix - Allahabad High Court Judgment Information System ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

JUDGMENT/ORDER IN - WRIT - C No. 37443 of 2011 at <strong>Allahabad</strong> Dated-21.10....http://elegalix.allahabadhighcourt.in/elegalix/WebShow<strong>Judgment</strong>.doPage 170 of 19710/21/2011The submission of Shri S.P. Gupta, learned Senior Advocate appearing for the intervenors, that since the landowners have not objected against the dispensation of inquiry by invoking Sections 17 (1) and 17 (4), of the Act,1894 it will be presumed that that the petitioners have waived their right to challenge the notifications does notcommand us. The right of objection to land owners is provided under Section 5A of the Act, 1894 after apreliminary notification is issued under Section 4 of the Act, proposing to acquire any land. When the right ofobjection under Section 5A of the Act, 1894 has been dispensed with by invoking Section 17(4) of the Act, 1894petitioners have no right to file objections. The question of waiver of right to file objection would have arisen if theland owners had right of objection under Section 5A of the Act, 1894 and they did not avail the same. There beingno right of objection, the question of waiver does not arise. Shri S.P. Gupta, then contended that it was open forthe land owners to raise their objections before the State Government objecting the dispensation of inquiry. Thesaid submission of Shri S.P. Gupta does not have our approval since there is no forum provided before the StateGovernment asking the petitioners to go before the State Government and raise objections failing which they shallbe treated to have waived their right to challenge the acquisition is misconceived.The principle of waiver has been elaborately dealt with and considered by the Apex <strong>Court</strong> in Sikkim SubbaAssociates Vs. State of Sikkim, (2001) 5 SCC 629.The Apex <strong>Court</strong> defined the principle of waiver in paragraph 16 in following words."Waiver involves a conscious, voluntary and intentional relinquishment or abandonment of a known, existing legalright, advantage, benefit, claim or privilege, which except for such a waiver, the party would have enjoyed".The submission of Shri S.P. Gupta that the petitioners accepting the compensation under the 1997 Rules hencethey shall be treated to have waived their right to challenge the acquisition now needs to be considered.From the materials brought on record, it does appear that the majority of land owners have accepted thecompensation under the 1997 Rules.1997 Rules, have been framed by the State of U.P. under Section 11 sub-section 2. The circumstances underwhich the petitioners have accepted the compensation under the 1997 Rules, have been explained in several writpetitions. It is useful to refer to the pleadings in the writ petition in that regard.In Writ Petition No.45694/2011, Jai Singh & Ors Vs. State of U.P.& Ors, the petitioners have challenged thenotifications dated 30/3/2002 and 28/6/2003 issued under Sections 4 and 6 and the award dated 29/1/2010. Thepetitioners have pleaded in the writ petition that the Additional District Magistrate, (Land Acquisition) GautamBudh Nagar sent a printed notice to the petitioners to appear before the Additional District Magistrate, (LandAcquisition) Gautam Budh Nagar for payment of compensation. When the petitioners appeared they wereinformed that they would be paid compensation at the rate of Rs. 378.92 per Square Yard of the acquired land.Petitioners did not agree to accept the said compensation and then they were told that the land having alreadybeen vested in the State, petitioners shall be deprived from receiving the compensation for long time and theyhave no option but to accept the compensation. Petitioners have further pleaded that the award under Section 11is passed after 7 to 8 years of the declaration during which the petitioners had been deprived of their land andenjoyment of their property. It is useful to quote paragraph 16 and relevant portion of paragraph 46 which are tobe following effect:-"16.That the Additional District Magistrate, (Land Acquisition) Gautam Budh Nagar sent a printed notice to thepetitioners intimating that their land situated in Village Sadarpur is needed for panned industrial Development.Petitioners in pursuance of the aforesaid notice appeared before the Additional District Magistrate, (LandAcquisition) Gautam Budh Nagar, then they have been told by the Authority officials that the Authority intended topay compensation @ Rs. 378.92 per sq yard of the acquired land. Petitioners were not agreed to the aforesaidrate of the land, but the officials of the Authority threatened them that since the land is vested into the StateGovernment and you people will be deprived from receiving the compensation for long time, you have no optionexcept to accept the said compensation, petitioners being afraid of, have accepted 90% compensation andentered into agreement.46. That the statutory authority has taken 7 to 8 years in passing the impugned award which is unexplained delay.The delay in making the said award deprived the land owners/petitioners of the enjoyment of their property or todeal with the land and delay in making the said award has subjected the owners of the land to untold hardship."In the present case, the award under Section 11 was declared on 29/1/2010 which has been filed as Annexure-4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!