La Red de Alta Velocidad Europea: Más un mosaico poco efectivo que una realidad

El presente comunicado de prensa tiene por objeto ofrecer una síntesis del contenido esencial del informe especial del Tribunal de Cuentas Europeo. El texto íntegro del informe puede consultarse en www.eca.europa.eu.

El presente comunicado de prensa tiene por objeto ofrecer una síntesis del contenido esencial del informe especial del
Tribunal de Cuentas Europeo.
El texto íntegro del informe puede consultarse en www.eca.europa.eu.

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

35<br />

Table 5 - Overview of costs per km and comparison with estimates<br />

Audited line<br />

Total<br />

length<br />

(km)<br />

Total<br />

cost<br />

(million<br />

euro)**<br />

Initial<br />

estimated<br />

cost<br />

(million<br />

euro)<br />

Actual<br />

cost<br />

overr<strong>un</strong><br />

(%)<br />

Initial<br />

construction<br />

cost per km<br />

(million euro)<br />

Final<br />

completion<br />

cost per km<br />

(million euro)<br />

Berlin-M<strong>un</strong>ich 671 14 682 8 337 76.1 % 12.4 21.9<br />

Stuttgart-M<strong>un</strong>ich 267 13 273 1 838 622.1 % 6.9 49.7<br />

Rhin-Rhône 138 2 588 2 053 26.1 % 14.9 18.8<br />

LGV Est Européenne 406 6 712 5 238 28.1 % 12.9 16.5<br />

Madrid-Barcelona-<br />

French Bor<strong>de</strong>r 797 12 109 8 740 38.5 % 11.0 15.2<br />

Eje Atlántico 165 2 596 2 055 26.3 % 12.5 15.7<br />

Madrid-León 345 5 415 4 062 33.3 % 11.8 15.7<br />

Madrid-Galicia* 416*** 5 714*** n/a n/a n/a 13.7***<br />

Turin-Salerno* 1 007 32 169 n/a n/a n/a 31.9<br />

Milan-Venice* 273 11 856 n/a n/a n/a 43.4<br />

*No cost estimates available at line level, so impossible to estimate potential overr<strong>un</strong>s.<br />

**As of the time of the audit and also for non-completed lines: Stuttgart-M<strong>un</strong>ich, Madrid-Galicia and<br />

Milan-Venice.<br />

***Calculated on a stretch Medina <strong>de</strong>l Campo-Galicia and therefore excluding the 133 km of overlap<br />

with Madrid-León HSL.<br />

Source: ECA. All figures are expressed in nominal terms.<br />

54. Delays at project level were also significant: eight of the 30 projects we audited had<br />

been <strong>de</strong>layed by at least one year, and half of the lines (five lines out of the ten audited) had<br />

experienced <strong>de</strong>lays of more than one <strong>de</strong>ca<strong>de</strong>. The Milan-Venice line is forecast to have the<br />

longest <strong>de</strong>lay compared to initial estimates (18 years).<br />

55. The highest project cost overr<strong>un</strong> was 83 %, for the “Stuttgart 21” station (Picture 2),<br />

which received 726.6 million euro in grants from the EU.