an Estimate<br />
The Horse Before the Cart Method<br />
This method requires an estimator to<br />
have an idea of what the cost of construction<br />
will be either through development of a<br />
conceptual estimate, updating an estimate of a<br />
similar project or use of a valuation service such<br />
as Marshall & Swift. A percentage of the cost<br />
of construction is then applied to arrive at the<br />
sum of funds to be allocated to estimating. (See<br />
the attached chart). This sum then is divided<br />
by the hourly rate paid the estimator, or the<br />
sum of the hourly rates paid to an estimating<br />
staff, to arrive at the total man-hours required.<br />
If a bid date has been set then the man-hours<br />
are converted to days and worked backward to<br />
indicate the date the estimator or estimating<br />
staff must receive drawings if the estimate is<br />
to be ready in time. Good practice is to allow<br />
extra days for review prior to submitting a bid.<br />
The Sheet Count Method<br />
As the title indicates this method<br />
involves counting the drawings that will be<br />