Specific requirements

Ensure gas production, e.g. by regular

feedstock input

Ensure that the enclosure is leak-tight

and stable

Monitor the fill level of the substrate and if

necessary shut off withdrawal from the liquid

phase (gas isolation point)

Ensure operation with positive pressure even

in the event of a sudden drop in temperature,

e.g. by means of

i. suitable gas displacement with respect

to the gas storage tank(s)

ii. constant monitoring of gas overpressure

in the interior and gas withdrawal

iii. sufficiently variable volume of the gas

storage tank

In addition, where inflatable double layer roofs

are used: ensure that the supporting air pressure

is lower than the pressure in the gas storage

tank, and ensure that the inner membrane is

leak-tight and stable.

No zoning necessary, unless the manufacturer’s

instructions specify different classification of

zones.

In the event that the above-mentioned requirements

are in place without all measures to monitor and

safeguard positive gas pressure being implemented,

the following conditions apply:

The occurrence of potentially explosive atmospheres

is identified, and measures are taken to

ensure that such atmospheres occur only rarely

and for short periods.

Zone 2: above the surface of the substrate in

the interior

Foreseeable disruptions or process-related operating

states that occur occasionally can allow air to

enter the interior of the digester, resulting in concentrations

falling below the UEL.

The occurrence of potentially explosive atmospheres

is occasionally possible.

Zone 1: above the surface of the substrate in

the interior

Agitators and ducts for agitator shafts and adjusters

for agitators, e.g. cable mechanisms

Submersible-motor agitators and submersiblemotor

pumps should comply with degree of protection

IP 68 according to DIN EN 60529. Material

requirements relating to corrosion, shear forces and

thermal stability should be taken into account when

selecting the agitators.

Ducts, technically leak-tight, in combination

with regular checks and maintenance, or the

agitator penetration below the surface of the

liquid/substrate.

No zoning necessary.

Ducts, technically leak-tight and above the

surface of the liquid/substrate.

Zone 2: 1 m around penetration.

Overflow aid

Overflow aid with screw conveyor.

Zone: as in downstream gas space.

Pressure surge overflow aid with physical limitation

of the injected air (volume limitation and

flow rate limitation).

Zone 0: in the pipe and in the vicinity of the

overflow.

Pressure surge overflow aid without physical

limitation of the injected air.

Zone 0: in the pipe and in the digester.

Surroundings of sight glasses in inside spaces

Bull’s eyes and observation windows must be

fitted in a leak-tight mounting in the digester

and permanently technically leak-tight according

to manufacturer’s declaration.

No zone.

Sight glass technically leak-tight, routine leak

checks in accordance with manufacturer’s

instructions.

No zone.

Sight glass technically leak-tight, but no routine

leak checks.

Zone 1: immediate vicinity.

Zone 2: remaining area.

Digestate storage with connection to gas system

Prevent air entering the gas system in the following

ways:

Ensure operation with positive pressure even

during removal of digestion products, e.g. by

constant monitoring of gas overpressure in the

interior and shutting off gas extraction pipes and

extraction points from the liquid phase;

Planned, monitored removal of digestion products,

especially by

ZZ

ensuring gas supply,

ZZ

visual inspection for ethylene propylene diene

monomer (EPDM) rubber membranes or gas

fill level monitoring for double membrane

systems or rigid gas storage tanks,