PARTNER ARTICLE<br />

the calculation indicates that using<br />

the same amount of resources with<br />

improved OEE will decrease cost per<br />

unit, since fixed cost will be spread over<br />

more units. Increasing OEE strategically<br />

points to improving maintenance<br />

work, specifically decreasing corrective<br />

maintenance and breakdowns. It is best<br />

if we can set up work processes to prevent<br />

repairs altogether. We can prevent<br />

failures with good lubrication, correct<br />

installation, cleaning, good operating<br />

practices and correct design of equipment.<br />

To enable Planning and Scheduling<br />

of maintenance work (in addition<br />

to coordination with the production<br />

plan) there must be good Condition<br />

Monitoring (inspections) of equipment.<br />

Condition Monitoring provides<br />

lead time for Planning and Scheduling<br />

by finding failures early before they<br />

develop into breakdowns. The failures<br />

found by Condition Monitoring should<br />

be prioritized according to defined priority<br />

rules.<br />

There is now a project to utilize<br />

machine learning that installs sensors<br />

and downloads software for some of<br />

the manufacturing equipment. Craftspeople<br />

and Reliability Engineers have<br />

already started to use that information<br />

to improve their PM programs<br />

by identifying and correcting conditions<br />

that eventually lead to failure of<br />

components. In fact, the maintenance<br />

organization has direct access to the<br />

machine learning database while they<br />

are inspecting, troubleshooting, or trying<br />

to find the root cause of a failure on<br />

their tablets and laptops.<br />

Technical Database:<br />

In an effort to improve OEE, Maintenance<br />

realized that there must be a<br />

good technical database and stores to<br />

enable effective planning. The technical<br />

database that includes OEM helps<br />

the planner find instructions, materials,<br />

spares, and technical specifications.<br />

Information such as clearances, set<br />

points, torque specs, etc. needs to be<br />

included in the work order packages.<br />

Stores must be well organized to protect<br />

the condition of parts. The Bill of<br />

Materials, as part of a technical database,<br />

must be complete and up to date<br />

to ensure that information is known,<br />

and correct parts are allocated to the<br />

job. This process will decrease the<br />

amount of time spent tracking down<br />

manuals, ordering parts and executing<br />

corrective maintenance work, allowing<br />

us to focus on improving OEE.<br />

Do:<br />

Once the job is planned and scheduled,<br />

the repair is executed at high quality.<br />

The craftspeople meet with the supervisor<br />

for 15 minutes in the morning<br />

to see if there are any changes to the<br />

schedule. The schedule is posted in the<br />

maintenance shop, but all the craftspeople<br />

have the schedule up on their<br />

tablets. The schedule shows start and<br />

stop times of each job and downtime<br />

of equipment coordinated with Operations<br />

and agreed upon by the Operations<br />

and Maintenance Coordinator<br />

(OMC). The OMC is the one point of<br />

contact between Maintenance and Operations.<br />

Record:<br />

After the work is completed, the job<br />

history is recorded in the CMMS. Recording<br />

work order history will answer:<br />

What was the problem? What was done<br />

to repair the problem? How can it be<br />

prevented in the future? The craftsperson<br />

has the flexibility to do this though<br />

their tablet, phone, or laptop. Since<br />

craftspeople update the work order history<br />

daily, the maintenance schedule is<br />

up to date in real time. This helps the<br />

Figure 1: IDCON's Circle of<br />

Continuous Improvement<br />

44 maintworld 3/<strong>2021</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!