26.12.2012 Views

Transocean Proxy Statement and 2010 Annual Report

Transocean Proxy Statement and 2010 Annual Report

Transocean Proxy Statement and 2010 Annual Report

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Performance <strong>and</strong> Other Key Indicators<br />

Contract backlog—The following table presents our contract backlog, including firm commitments only, for our contract drilling<br />

services segment as of February 10, 2011, October 14, <strong>2010</strong> <strong>and</strong> December 31, 2009. Firm commitments are represented by signed<br />

drilling contracts or, in some cases, by other definitive agreements awaiting contract execution. Our contract backlog is calculated by<br />

multiplying the full contractual operating dayrate by the number of days remaining in the firm contract period, excluding revenues for<br />

mobilization, demobilization <strong>and</strong> contract preparation or other incentive provisions, which are not expected to be significant to our contract<br />

drilling revenues. The contractual operating dayrate may be higher than the actual dayrate we receive or we may receive other dayrates<br />

included in the contract, such as a waiting-on-weather rate, repair rate, st<strong>and</strong>by rate or force majeure rate. The contractual operating<br />

dayrate may also be higher than the actual dayrate we receive because of a number of factors, including rig downtime or suspension of<br />

operations. In certain contracts, the dayrate may be reduced to zero if, for example, repairs extend beyond a stated period of time.<br />

AR-42<br />

February 10,<br />

2011<br />

October 14,<br />

<strong>2010</strong><br />

December 31,<br />

2009<br />

Contract backlog (in millions)<br />

High-Specification Floaters $ 20,956 $ 22,107 $ 25,704<br />

Midwater Floaters 1,912 2,320 3,412<br />

High-Specification Jackups 129 335 374<br />

St<strong>and</strong>ard Jackups 936 1,251 1,601<br />

Other Rigs 47 55 80<br />

Total $ 23,980 $ 26,068 $ 31,171<br />

We have 12 rigs under contract <strong>and</strong> operating in the U.S. Gulf of Mexico. The backlog associated with the contracts relating to<br />

these rigs was $6.6 billion as of February 10, 2011, of which $2.2 billion could be lost if our customers are legally permitted to <strong>and</strong> choose<br />

to exercise their termination rights under certain contracts.<br />

Although Deepwater Horizon was operating under a contract, which was to extend through September 2013, the total loss of the<br />

rig resulted in an automatic termination of the agreement. At the time of the Macondo well incident, the backlog associated with the<br />

Deepwater Horizon drilling contract was approximately $590 million.<br />

The firm commitments that comprise the contract backlog for our contract drilling services segment are presented in the following<br />

table along with the associated average contractual dayrates measured at February 10, <strong>2010</strong>. The actual amounts of revenues earned<br />

<strong>and</strong> the actual periods during which revenues are earned will differ from the amounts <strong>and</strong> periods shown in the tables below due to various<br />

factors, including shipyard <strong>and</strong> maintenance projects, unplanned downtime <strong>and</strong> other factors that result in lower applicable dayrates than<br />

the full contractual operating dayrate. Additional factors that could affect the amount <strong>and</strong> timing of actual revenue to be recognized <strong>and</strong><br />

timing include customer liquidity issues <strong>and</strong> contract terminations, which are available to our customers under certain circumstances. The<br />

contract backlog average contractual dayrate is defined as the contracted operating dayrate to be earned per revenue earning day in the<br />

period. A revenue earning day is defined as a day for which a rig earns a dayrate during the firm contract period after commencement of<br />

operations.<br />

For the years ending December 31<br />

Total 2011 2012 2013 2014 Thereafter<br />

Contract backlog (In millions, except average dayrates)<br />

High-Specification Floaters $ 20,956 $ 5,710 $ 5,660 $ 4,511 $ 2,503 $ 2,572<br />

Midwater Floaters 1,912 949 545 170 98 150<br />

High-Specification Jackups 129 104 25 — — —<br />

St<strong>and</strong>ard Jackups 936 536 241 112 38 9<br />

Other Rigs 47 23 24 — — —<br />

Total contract backlog $ 23,980 $ 7,322 $ 6,495 $ 4,793 $ 2,639 $ 2,731<br />

Average contractual dayrates Total 2011 2012 2013 2014 Thereafter<br />

High-Specification Floaters $ 466,000 $ 471,000 $ 472,000 $ 476,000 $ 466,000 $ 429,000<br />

Midwater Floaters 318,000 325,000 342,000 294,000 268,000 268,000<br />

High-Specification Jackups 103,000 103,000 100,000 — — —<br />

St<strong>and</strong>ard Jackups 97,000 107,000 89,000 82,000 81,000 78,000<br />

Other Rigs 72,000 72,000 72,000 — — —<br />

Total fleet average $ 383,000 $ 342,000 $ 385,000 $ 420,000 $ 425,000 $ 410,000

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!