Transocean Proxy Statement and 2010 Annual Report
Transocean Proxy Statement and 2010 Annual Report
Transocean Proxy Statement and 2010 Annual Report
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Performance <strong>and</strong> Other Key Indicators<br />
Contract backlog—The following table presents our contract backlog, including firm commitments only, for our contract drilling<br />
services segment as of February 10, 2011, October 14, <strong>2010</strong> <strong>and</strong> December 31, 2009. Firm commitments are represented by signed<br />
drilling contracts or, in some cases, by other definitive agreements awaiting contract execution. Our contract backlog is calculated by<br />
multiplying the full contractual operating dayrate by the number of days remaining in the firm contract period, excluding revenues for<br />
mobilization, demobilization <strong>and</strong> contract preparation or other incentive provisions, which are not expected to be significant to our contract<br />
drilling revenues. The contractual operating dayrate may be higher than the actual dayrate we receive or we may receive other dayrates<br />
included in the contract, such as a waiting-on-weather rate, repair rate, st<strong>and</strong>by rate or force majeure rate. The contractual operating<br />
dayrate may also be higher than the actual dayrate we receive because of a number of factors, including rig downtime or suspension of<br />
operations. In certain contracts, the dayrate may be reduced to zero if, for example, repairs extend beyond a stated period of time.<br />
AR-42<br />
February 10,<br />
2011<br />
October 14,<br />
<strong>2010</strong><br />
December 31,<br />
2009<br />
Contract backlog (in millions)<br />
High-Specification Floaters $ 20,956 $ 22,107 $ 25,704<br />
Midwater Floaters 1,912 2,320 3,412<br />
High-Specification Jackups 129 335 374<br />
St<strong>and</strong>ard Jackups 936 1,251 1,601<br />
Other Rigs 47 55 80<br />
Total $ 23,980 $ 26,068 $ 31,171<br />
We have 12 rigs under contract <strong>and</strong> operating in the U.S. Gulf of Mexico. The backlog associated with the contracts relating to<br />
these rigs was $6.6 billion as of February 10, 2011, of which $2.2 billion could be lost if our customers are legally permitted to <strong>and</strong> choose<br />
to exercise their termination rights under certain contracts.<br />
Although Deepwater Horizon was operating under a contract, which was to extend through September 2013, the total loss of the<br />
rig resulted in an automatic termination of the agreement. At the time of the Macondo well incident, the backlog associated with the<br />
Deepwater Horizon drilling contract was approximately $590 million.<br />
The firm commitments that comprise the contract backlog for our contract drilling services segment are presented in the following<br />
table along with the associated average contractual dayrates measured at February 10, <strong>2010</strong>. The actual amounts of revenues earned<br />
<strong>and</strong> the actual periods during which revenues are earned will differ from the amounts <strong>and</strong> periods shown in the tables below due to various<br />
factors, including shipyard <strong>and</strong> maintenance projects, unplanned downtime <strong>and</strong> other factors that result in lower applicable dayrates than<br />
the full contractual operating dayrate. Additional factors that could affect the amount <strong>and</strong> timing of actual revenue to be recognized <strong>and</strong><br />
timing include customer liquidity issues <strong>and</strong> contract terminations, which are available to our customers under certain circumstances. The<br />
contract backlog average contractual dayrate is defined as the contracted operating dayrate to be earned per revenue earning day in the<br />
period. A revenue earning day is defined as a day for which a rig earns a dayrate during the firm contract period after commencement of<br />
operations.<br />
For the years ending December 31<br />
Total 2011 2012 2013 2014 Thereafter<br />
Contract backlog (In millions, except average dayrates)<br />
High-Specification Floaters $ 20,956 $ 5,710 $ 5,660 $ 4,511 $ 2,503 $ 2,572<br />
Midwater Floaters 1,912 949 545 170 98 150<br />
High-Specification Jackups 129 104 25 — — —<br />
St<strong>and</strong>ard Jackups 936 536 241 112 38 9<br />
Other Rigs 47 23 24 — — —<br />
Total contract backlog $ 23,980 $ 7,322 $ 6,495 $ 4,793 $ 2,639 $ 2,731<br />
Average contractual dayrates Total 2011 2012 2013 2014 Thereafter<br />
High-Specification Floaters $ 466,000 $ 471,000 $ 472,000 $ 476,000 $ 466,000 $ 429,000<br />
Midwater Floaters 318,000 325,000 342,000 294,000 268,000 268,000<br />
High-Specification Jackups 103,000 103,000 100,000 — — —<br />
St<strong>and</strong>ard Jackups 97,000 107,000 89,000 82,000 81,000 78,000<br />
Other Rigs 72,000 72,000 72,000 — — —<br />
Total fleet average $ 383,000 $ 342,000 $ 385,000 $ 420,000 $ 425,000 $ 410,000