Figure 10: Supplier process flow chart<br />
Quotations will be<br />
produced within<br />
10 Days<br />
Manufacturing Lead Time is<br />
42 Days<br />
From receipt of order to first day<br />
on site<br />
Approved Drawings issued to<br />
Supplier by Regional Works<br />
Contractor<br />
2.27 Suppliers were also able to feedback on the areas for improvement in advance of the<br />
next phase. For example, Allan Nuttall Ltd. provided an clear presentation of commonly<br />
encountered problems with the installation of interview screens and booths including:<br />
• Runs of several booths set out staggered to suit local site conditions<br />
• Adjacent walls had insufficient length to accept bulkhead<br />
• Various assortment of CAD blocks used some showing desks with return tops<br />
• Mechanical ducting installed too low, fouling bulkhead<br />
• Product size altered to suit local conditions<br />
• Structural objects fouling installation area<br />
• Ceilings Installed prior to our installation<br />
• Varying sizes of structural openings.<br />
2.28 Figure 11 shows how an existing structural column and a flank wall which is too short<br />
results in modifications to the:<br />
• Desktop<br />
• Modesty panel<br />
• Canopy Sub Frame<br />
• Canopy Bulkhead & Fascia Panels<br />
• Glass Mounting Trough<br />
• Position Closed Blind.<br />
Supplier prepare<br />
Quotation<br />
Order Received<br />
Product Manufacture<br />
Site Installation<br />
Site Survey<br />
(Health & Safety)<br />