5. CONSTRUCTION SCHEDULE AND MAJOR MILESTONES<br />
<strong>Qinshan</strong> Unit 1 was based on a 72-month schedule, followed 9 months later by <strong>Qinshan</strong> Unit 2.<br />
It is to be noted that Unit 1 achieved In-Service 43 days ahead of schedule. Figure 5-1 provides<br />
major <strong>Project</strong> milestone data.<br />