2003 February<br />

8. METHODS AND FEATURES TO COMPLETE THE WORK ON<br />

SCHEDULE AND ON BUDGET<br />

8.1 <strong>Construction</strong> Issues<br />

The major challenge of this first <strong>CANDU</strong> <strong>Project</strong> in China was construction by new contractors<br />

not familiar with AECL or international practices. AECL recognized that it would have to use<br />

<strong>and</strong> enhance its most modern management systems <strong>and</strong> tools to ensure success of the <strong>Qinshan</strong><br />

<strong>Project</strong>. Timesaving elements such as open top construction <strong>and</strong> modular construction for major<br />

components were successfully implemented. The strong focus on project <strong>and</strong> construction<br />

management <strong>and</strong> partnership among TQNPC, AECL, subcontractors <strong>and</strong> the Chinese<br />

construction contractors was a success.<br />

Key features of the Site include four undersea intake ducts averaging 50 meters long. These<br />

ducts were constructed in water having a high silt content <strong>and</strong> current velocities reaching<br />

4 meters per second with the inflow of the tide into Hangzhou Bay where the <strong>Qinshan</strong> Site is<br />

located. A major challenge for both BOP <strong>and</strong> NSP was the localization of structural steel design,<br />

fabrication <strong>and</strong> erection, as most experience in China had been with concrete structures.<br />

A special task was to build retaining walls around the Site, which is surrounded by water on three<br />

sides to create sufficient real estate for the two units. This made execution <strong>and</strong> co-ordination of<br />

work difficult <strong>and</strong> greatly increased the need for planning <strong>and</strong> co-ordination among the<br />

contractors.<br />

8.1.1 Degree of Prefabrication/Modularization<br />

Prefabrication <strong>and</strong> modularization were effective in ensuring the timely completion of<br />

construction. The lower dome was fully assembled on the ground, painted <strong>and</strong> lifted into<br />

position using a very heavy lift crane. This major element of work enabled significant progress<br />

to be achieved on the installation of the reactivity deck <strong>and</strong> related components inside the<br />

Reactor Building. <strong>Construction</strong> of the lower dome in situ would have required suspension of<br />

reactivity deck installation for safety <strong>and</strong> protection of the equipment below. This resulted in a<br />

significant time saving for the <strong>Project</strong>. Another module was the dousing steel along with all<br />

piping, tanks, valves, <strong>and</strong> electrical <strong>and</strong> instrumentation, which resulted in a 3-month net saving<br />

over previous projects.<br />

8.1.2 Open Top <strong>Construction</strong><br />

In the past, a major challenge to efficient construction has been the work restrictions within the<br />

containment building. Historically, the Reactor Building or containment wall was constructed<br />

with openings left in the sides to allow entry of large equipment. To facilitate access at <strong>Qinshan</strong><br />

Phase III, a temporary roof with strategically located openings was placed on top of each reactor<br />

building (open top construction). A very heavy lift crane supplied by TQNPC placed major<br />

pieces of equipment directly into their final positions through these openings, gaining significant<br />

schedule improvements. A steam generator installation by the open top method took only two<br />

days against the two weeks taken by the traditional horizontal-access method. About 70 pieces<br />

of equipment were set in place using the heavy lift crane, simplifying access <strong>and</strong> allowing work<br />

to start or continue in other areas, thus reducing labour <strong>and</strong> risks associated with installation.<br />