Electricity Ten Year Statement - National Grid
Electricity Ten Year Statement - National Grid
Electricity Ten Year Statement - National Grid
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
2.5<br />
Plant margins<br />
This section brings together the information<br />
described earlier in this chapter on demand<br />
projections and future generation capacity mix<br />
and assesses the status of future generation<br />
projects and the ‘plant margin’ assumed in the<br />
different energy scenarios. The plant margin is<br />
defined as the amount of generation capacity<br />
available over and above the level of peak demand.<br />
2.5.1<br />
Project Status<br />
Figure 2.5.1 shows the current status of the<br />
projects included in the contracted generation<br />
background. These categories are broadly defined<br />
as follows:<br />
Existing – this is the level of generation capacity<br />
already built and commercially generating.<br />
Under Construction – the level of generation<br />
capacity which is currently being built.<br />
Consents Approved – generation projects that<br />
have obtained the relevant consents to proceed.<br />
Awaiting Consents – these are generation<br />
projects that have applied for the relevant<br />
consents to proceed but are awaiting a decision.<br />
Scoping – these are projects that have a signed<br />
connection agreement only but have not yet<br />
applied for any consents.<br />
Page 28<br />
In addition Figure 2.5.1 includes the level of<br />
‘existing’ generation assumed in each of the<br />
three energy scenarios. These figures include<br />
assumptions on plant closures within each of the<br />
scenarios and highlights when new generation will<br />
be required in these scenarios. This is explored<br />
further in the assessment of plant margins later<br />
in this section, but the impact of environmental<br />
legislation and ageing plant can be seen as<br />
existing generation falls due to these plant closures.<br />
A significant proportion of the contracted<br />
generation is in the scoping phase, with the<br />
majority of this being low-carbon generation such<br />
as offshore wind and new nuclear plant. Around<br />
15 GW of plant has the relevant consents with just<br />
over 9 GW of this being CCGT plant.