PRESENT STATUS:<br />

• Detailed Engineering Design of Diamer Basha Dam <strong>Project</strong> (DBDP) was completed in June-2008.<br />

• PC-I <strong>for</strong> Land Acquisition and Resettlement was approved by Executive Committee of National Economic<br />

Council (ECNEC) on 6.11.2008 <strong>for</strong> Rs. 60 billion.<br />

• Main PC-I <strong>for</strong> DBDP was approved by ECNEC on 20.08.2009 <strong>for</strong> Rs.894.257 billion.<br />

• Resolution on Consensus of Diamer Basha Dam <strong>Project</strong> approved from Council of Common Interest (CCI)<br />

on 18.07.2010 headed by Prime Minister of Pakistan.<br />

• Bridge at Thakot on Indus River is completed by NHA <strong>for</strong> transportation of material and heavy machinery<br />

<strong>for</strong> construction of Diamer Basha Dam <strong>Project</strong>.<br />

• Priority Land Acquisition has started.<br />

• Rs.6.563 billion have been released to the Government of Gilgit-Baltistan <strong>for</strong> acquisition of land and 1783<br />

Acres of land has been acquired.<br />

• Rs.262 million was released in to D.C. Kohistan <strong>for</strong> acquisition of land and 162 Acres land has been acquired<br />

of Khyber Pakhtunkhwa area.<br />

• A vocational Training Institute has been setup.<br />

• Inauguration ceremony <strong>for</strong> commencement of works of Diamer Basha Dam <strong>Project</strong> has been carried out by<br />

the Prime Minister of Pakistan on 18.10.2011.<br />

PROJECT IMPLEMENTATION<br />

Implementation of the dam appurtenant structures shall be through international competitive bidding<br />

comprising of the following five lots:-<br />

Sr.<br />

No.<br />

Description of work Local Foreign<br />

1. Contract Lot-1<br />

(Concrete Dam and Related Structures including<br />

Diversion Tunnels and Permanent Access Bridge)<br />

2. Contract Lot-2<br />

(Underground Works and Related Structures (Left<br />

and Right Banks)<br />

3. Contract Lot-3<br />

(Hydro-Mechanical Equipment and Hydraulic Steel<br />

Structures)<br />

4. Contract Lot-4<br />

(Power Plant Generation Equipment (Left and Right<br />

Bank)<br />

Total<br />

Cost<br />

US$ Million<br />

Const.<br />

Period<br />

(Yrs.)<br />

1,096 731 1,827 9<br />

512 173 685 6.4<br />

42 380 422 8<br />

103 927 1,030 7<br />

5. Contract Lot-5<br />

(Electrical High Voltage Equipment and Power Plant<br />

Electrical Equipment (Left and Right Bank).<br />

109 954 1,063 7<br />

Total 1,862 3165 5,027<br />

Strategy<br />

• After approval of FODP/ADB Report on Water Sector Task Force by Federal Cabinet new strategy to be<br />

adopted.<br />

• In view of the reluctance of World Bank/ADB <strong>for</strong> financing Diamer Basha Dam <strong>Project</strong> an alternate financing<br />

plan needs to be prepared.<br />

• GoP to provide funds <strong>for</strong> land acquisition.<br />

• 80% of the cost of project will be met through loan/supplier credit/buyer’s credit.<br />

• 20% of the cost of the project will be met through Govt. funding, domestic loan/local bonds (Sukuk) and<br />

PSDP.<br />

• Foreign financing will be made through Donor Agency/ADB//IDB/Middle East Donors/Buyer Credits/Supplier’s<br />

Credit<br />

• Special request will be made to Islamic Development Bank, Asian Development Bank, Kuwait Development<br />

Fund, Saudi Development Fund, Qatar Development Fund, Abu Dhabi Fund <strong>for</strong> investing in Diamer Basha<br />

Dam <strong>Project</strong>.<br />

• Special request may be made to <strong>USAID</strong> to support this project as signatory project in Pakistan.<br />

• Consortium will be made comprising of Chinese Turkish and other Civil Contractors.<br />

• Consortium will also be made <strong>for</strong> supplying Electro-Mechanical equipment as Supplier’s Credit.<br />