KHAN KHWAR HYDROPOWER PROJECT<br />

♦ Location Khan Khwar River, A Tributary of Indus River in District<br />

Shangla (Khyber Pakhtunkhwa)<br />

♦ Salient Features � Dam Height<br />

30 m<br />

� Length of Headrace<br />

Tunnel<br />

� Gross Head<br />

� Objectives<br />

� Installed Capacity<br />

� Annual Energy<br />

� EIRR<br />

4540 m<br />

257 m<br />

To Generate Electricity<br />

72 MW<br />

306 GWh<br />

29.56%<br />

♦ Scope of Work The project envisages installation of 72 MW Hydropower<br />

plant along with allied transmission and grid facility. The<br />

plant will generate 306 GWh/annum of electricity.<br />

♦ Consultants HHH Consultants, NDC, LAHMEYER, BARQAAB, BAK,<br />

PES, EGC, RC, IDC & DMC<br />

♦ Contractor CWH-HE, DEC<br />

♦ Execution by WAPDA<br />

♦ Date of Commencement June, 2003<br />

♦ Date of Completion Actual June 2006 / Expected March 2012 (MoU-2)<br />

♦ Financial Status Local FEC Total (Rs. Million)<br />

Original PC-I Cost 2,718.607 2,644.098 5,362.705<br />

Revised PC-I Cost 4,573.688 3,727.791 8,301.479<br />

Expenditures upto 30.6.2012 4,927.132 4,301.934 9,229.066<br />

PSDP Allocation 2012-2013 - - -<br />

Expenditure during the Month 4.820 - 4.820<br />

Current F/Y Expenditure 8.420 - 8.420<br />

Upto date Expenditure (O&M) *8.420 - *8.420<br />

* There is no PSDP Allocation <strong>for</strong> F/Y 2012-13. Expenditure is chargeable to O&M Budget.<br />

Physical Progress<br />

o Physical Progress 99.90 % against 100 %<br />

o Financial Progress *111.17 % against 100 % (upto 30.06.2012)<br />

* 2 nd revised PC-I cleared by CDWP at revised cost of Rs. 10,732.788 Million on 18.06.2012 [<br />

- Testing/commissioning of unit # 2 started on Oct, 04. 2010.<br />

- Testing/commissioning of unit # 1 started on Oct, 19. 2010.<br />

- Commercial operation started w.e.f. Nov 08, 2010.<br />

34