KHAN KHWAR HYDROPOWER PROJECT<br />
♦ Location Khan Khwar River, A Tributary of Indus River in District<br />
Shangla (Khyber Pakhtunkhwa)<br />
♦ Salient Features � Dam Height<br />
30 m<br />
� Length of Headrace<br />
Tunnel<br />
� Gross Head<br />
� Objectives<br />
� Installed Capacity<br />
� Annual Energy<br />
� EIRR<br />
4540 m<br />
257 m<br />
To Generate Electricity<br />
72 MW<br />
306 GWh<br />
29.56%<br />
♦ Scope of Work The project envisages installation of 72 MW Hydropower<br />
plant along with allied transmission and grid facility. The<br />
plant will generate 306 GWh/annum of electricity.<br />
♦ Consultants HHH Consultants, NDC, LAHMEYER, BARQAAB, BAK,<br />
PES, EGC, RC, IDC & DMC<br />
♦ Contractor CWH-HE, DEC<br />
♦ Execution by WAPDA<br />
♦ Date of Commencement June, 2003<br />
♦ Date of Completion Actual June 2006 / Expected March 2012 (MoU-2)<br />
♦ Financial Status Local FEC Total (Rs. Million)<br />
Original PC-I Cost 2,718.607 2,644.098 5,362.705<br />
Revised PC-I Cost 4,573.688 3,727.791 8,301.479<br />
Expenditures upto 30.6.2012 4,927.132 4,301.934 9,229.066<br />
PSDP Allocation 2012-2013 - - -<br />
Expenditure during the Month 4.820 - 4.820<br />
Current F/Y Expenditure 8.420 - 8.420<br />
Upto date Expenditure (O&M) *8.420 - *8.420<br />
* There is no PSDP Allocation <strong>for</strong> F/Y 2012-13. Expenditure is chargeable to O&M Budget.<br />
Physical Progress<br />
o Physical Progress 99.90 % against 100 %<br />
o Financial Progress *111.17 % against 100 % (upto 30.06.2012)<br />
* 2 nd revised PC-I cleared by CDWP at revised cost of Rs. 10,732.788 Million on 18.06.2012 [<br />
- Testing/commissioning of unit # 2 started on Oct, 04. 2010.<br />
- Testing/commissioning of unit # 1 started on Oct, 19. 2010.<br />
- Commercial operation started w.e.f. Nov 08, 2010.<br />