NAULONG DAM PROJECT<br />
LOCATION<br />
The proposed dam site is located on Mula river at Sunt about 30 kms from Gandawa City in tehsil and<br />
district Jhal Magsi (Balochistan).<br />
OBJECTIVES<br />
– Irrigated agriculture development of 47,000 acres of culturable command area.<br />
– Hydropower generation of 4.4MW.<br />
– Flood Mitigation.<br />
– Socio-economic uplift, poverty reduction and women emancipation.<br />
SALIENT FEATURES<br />
– Dam Type Earth fill<br />
– Dam Height 186 ft<br />
– Gross Storage 242,452 AF<br />
– Live Storage 200,000 AF<br />
– Culturable Command Area 47,000 acres<br />
– Power Generation 4.4 MW<br />
– Annual Energy 26.6 GWh<br />
– Revised <strong>Project</strong> Cost Rs. 18.028 billion<br />
CURRENT STATUS<br />
• Feasibility study and detailed engineering design of the <strong>Project</strong> completed in 2009.<br />
• PC-I amounting to Rs. 11.699 Billion approved by ECNEC in its meeting held on<br />
Sep. 3, 2009.<br />
• Tenders <strong>for</strong> construction received and opened on April 17, 2010. Letter of intent<br />
issued to the lowest bidder M/s. Descon – Zargoon JV on April 12, 2011. Letter of<br />
Acceptance issued on May 10, 2012.<br />
• During visit to China the President invited Chinese firms to participate <strong>for</strong><br />
construction of Naulong Dam <strong>Project</strong>.<br />
• Governor Balochistan and Chief Minister Balochistan assured Chinese Ambassador<br />
<strong>for</strong> providing full security arrangements <strong>for</strong> the construction firms especially the<br />
Chinese.<br />
• M/s Descon & Sinohydro of China have signed a joint venture agreement as<br />
contractor <strong>for</strong> construction of the project.<br />
• Memorandum of Understanding (MOU) <strong>for</strong> security arrangement <strong>for</strong> contractor<br />
concurred by Government of Balochistan.<br />
• Expression of Interest (EOI) <strong>for</strong> construction supervision of the <strong>Project</strong> received on<br />
June 25, 2012. Six (06) firms / JV’s submitted EOI documents and are under<br />
evaluation.<br />
• Revised PC-I amounting to Rs. 18.028 Billion approved by ECNEC in its meeting<br />
held on Aug. 16, 2012.<br />
26