ALLAI KHWAR HYDROPOWER PROJECT<br />
♦ Location On Allai Khwar, Left Tributary of Indus River near Besham<br />
in District Battagram, Khyber Pakhtunkhwa<br />
♦ Salient Features � Dam Height<br />
� Length of Headrace<br />
� Installed Capacity<br />
� Annual Energy<br />
� Gross Head<br />
� Objectives<br />
� EIRR<br />
32.50m<br />
2366 m<br />
121 MW<br />
463 GWh<br />
697 m<br />
To Generate Electricity<br />
23.97%<br />
♦ Execution by WAPDA<br />
♦ Consultants HHH Consultants NDC, LAHMEYER, BARQAAB,<br />
BAK, PES, EGC, RC, IDC & DMC<br />
♦ Contractor<br />
DEC Astron, VA Tech<br />
♦ Donor Agency Government of Pakistan<br />
♦ Date of Commencement June, 2003<br />
♦ Date of Completion Actual Jan 2009 / Revised Oct,2011<br />
Expected Oct, 2012<br />
♦ Financial Status Local FEC F/LOAN Total (Rs. M)<br />
Original PC-I Cost 5,124.284 3,453.540 - 8,577.824<br />
Revised PC-I Cost 7,312.687 6,522.261 - 13,834.948<br />
Expenditures upto 30.6.2012 5,261.974 3,327.478 2,315.596 10,905.048<br />
PSDP Allocation 2012-2013 804.000 725.000 644.000 2,173.000<br />
Expenditure During the Month 3.868 35.268 101.801 140.937<br />
Current F/Y Expenditure 6.868 197.706 179.534 384.108<br />
Upto date Expenditure 5,268.842 3,525.184 2,495.130 11,289.156<br />
o Physical Progress 94.00% against 98.00%<br />
o Financial Progress 81.60% against 81.44%<br />
Revised PC-I amounting to Rs. 13834.948 Million approved on 27.09.2011.<br />
30