lt8 I Delence Works Procedure, 2007<br />

feasibility of execution so as to ensure their completion<br />

during the same financial year.<br />

VIII. PROCESSING OF MAJOR CAPITAL WORKS<br />

@| There are nine main stages in the planning,<br />

sanctioning and execution of new Major Capital Works,<br />

vtz.<br />

(i) Demand for and Planning of New Works<br />

(ii) Acceptance of Necessity<br />

(iii) Preparation of Approximate Estimates<br />

(iv) Administrative Approval<br />

(v) Appropriation of Funds<br />

(vi) Technical Sanction<br />

(vii) Tender Action<br />

(viii)Contract Action<br />

(ix) Execution of Works<br />

The details of procedural requirements at each of<br />

these stages are explained below.<br />

IX. DEMAND FOR PLANNING OF NEW WORKS<br />

@<br />

Demands for new Major Capital works services<br />

will be submitted in the form of a Statement of Case to<br />

the Competent Financial Authority for consideration and<br />

approval. The Statement of Case will inter alia explain.:<br />

(a) The need for and scope of the works proposed.<br />

O) Whether, besides construction works, the proposed<br />

project includes procurement/manufaiture/<br />

installation/storage of new/special equipment or<br />

armaments, or setting up new operation related<br />

facility including special repairs and maintenance<br />

of capital assets with which the civil works have<br />

, to be integrated.<br />

(c) .The type of construction-authorized or special,<br />

permanent or temporary-required.<br />

Drlcnce Works Proceduro, 2007 [le]<br />

(d) The target date by which the completion of the<br />

proposed works are desired.<br />

(e) The desired location and availability of land, if<br />

any.<br />

(f) If land is not available, the time likely to be<br />

taken for obtaining the same and for site<br />

development, environment clearance etc.<br />

(g) Extent of enabling works and external scrvices<br />

or utilities of preparatory nature required.<br />

(h) Need for engaging an outside consultancy agency,<br />

if any, for the total project or any part thereof,<br />

viz., pre-and post-administrative approval<br />

planning, design, detailed engineering, project<br />

management, etc.<br />

(D A rough cost estimate in the format at Appendix'B'.<br />

0) An Engineer appreciation in the format at<br />

Appendix'C'.<br />

(a) After examination and approval of the<br />

Statement of Case, the Competent Financial Authority will<br />

convene a Recee-cum-Siting and Costing Board. Such Board<br />

Proceedings (BPs), while examining the various features of<br />

the new works proposal, will also deliberate on the need,<br />

if any, for compressing the normal time-frame of carrying<br />

out the works, issue of a 'go-ahead' sanction for preliminary<br />

works in case of works proposals costing more than Rs. 1<br />

Crore and delegation of special powers to the Chief<br />

Engineer for planning and execution of the works and<br />

make necessary recommendations.<br />

(b) The completed Board proceedings, as ordered by<br />

Comd. HQ, alongwith detailed engineer appreciation and<br />

rough cost estimates, will be required to be submitted<br />

within three months from the approval of Annual Works<br />

Programme in the following manner :