lt8 I Delence Works Procedure, 2007<br />
feasibility of execution so as to ensure their completion<br />
during the same financial year.<br />
VIII. PROCESSING OF MAJOR CAPITAL WORKS<br />
@| There are nine main stages in the planning,<br />
sanctioning and execution of new Major Capital Works,<br />
vtz.<br />
(i) Demand for and Planning of New Works<br />
(ii) Acceptance of Necessity<br />
(iii) Preparation of Approximate Estimates<br />
(iv) Administrative Approval<br />
(v) Appropriation of Funds<br />
(vi) Technical Sanction<br />
(vii) Tender Action<br />
(viii)Contract Action<br />
(ix) Execution of Works<br />
The details of procedural requirements at each of<br />
these stages are explained below.<br />
IX. DEMAND FOR PLANNING OF NEW WORKS<br />
@<br />
Demands for new Major Capital works services<br />
will be submitted in the form of a Statement of Case to<br />
the Competent Financial Authority for consideration and<br />
approval. The Statement of Case will inter alia explain.:<br />
(a) The need for and scope of the works proposed.<br />
O) Whether, besides construction works, the proposed<br />
project includes procurement/manufaiture/<br />
installation/storage of new/special equipment or<br />
armaments, or setting up new operation related<br />
facility including special repairs and maintenance<br />
of capital assets with which the civil works have<br />
, to be integrated.<br />
(c) .The type of construction-authorized or special,<br />
permanent or temporary-required.<br />
Drlcnce Works Proceduro, 2007 [le]<br />
(d) The target date by which the completion of the<br />
proposed works are desired.<br />
(e) The desired location and availability of land, if<br />
any.<br />
(f) If land is not available, the time likely to be<br />
taken for obtaining the same and for site<br />
development, environment clearance etc.<br />
(g) Extent of enabling works and external scrvices<br />
or utilities of preparatory nature required.<br />
(h) Need for engaging an outside consultancy agency,<br />
if any, for the total project or any part thereof,<br />
viz., pre-and post-administrative approval<br />
planning, design, detailed engineering, project<br />
management, etc.<br />
(D A rough cost estimate in the format at Appendix'B'.<br />
0) An Engineer appreciation in the format at<br />
Appendix'C'.<br />
(a) After examination and approval of the<br />
Statement of Case, the Competent Financial Authority will<br />
convene a Recee-cum-Siting and Costing Board. Such Board<br />
Proceedings (BPs), while examining the various features of<br />
the new works proposal, will also deliberate on the need,<br />
if any, for compressing the normal time-frame of carrying<br />
out the works, issue of a 'go-ahead' sanction for preliminary<br />
works in case of works proposals costing more than Rs. 1<br />
Crore and delegation of special powers to the Chief<br />
Engineer for planning and execution of the works and<br />
make necessary recommendations.<br />
(b) The completed Board proceedings, as ordered by<br />
Comd. HQ, alongwith detailed engineer appreciation and<br />
rough cost estimates, will be required to be submitted<br />
within three months from the approval of Annual Works<br />
Programme in the following manner :