04.08.2013 Views

department of power annual report 1991-92 - Ministry of Power

department of power annual report 1991-92 - Ministry of Power

department of power annual report 1991-92 - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Salient Features:<br />

A 260.5 metres high earth and rockfill dam, across<br />

the river Bhagirathi at Tehri, just after its confluence<br />

with river Bhilangana for creating a storage reservoir<br />

to generate <strong>power</strong> and provide irrigation facilities.<br />

• An underground <strong>power</strong> house <strong>of</strong> 1000 MW (4x250<br />

MW) capacity with conventional turbine-Generating<br />

sets under Stage-I at Tehri.<br />

• Second underground <strong>power</strong> house <strong>of</strong> 1000 MW<br />

(4x250 MW) capacity with reversible pump turbine<br />

sets under Stage-II at Tehri Pump Storage Plant).<br />

• A 103.5 metre high concrete dam (which will<br />

provide a balancing reservoir) with a surface <strong>power</strong><br />

house <strong>of</strong> 400 MW (4x100 MW) capacity at<br />

Koteshwar, 22 Km, downstream <strong>of</strong> Tehri dam site<br />

across the river Bhagirathi.<br />

• Transmission system for evacuation <strong>of</strong> <strong>power</strong><br />

generated Tehri at an Koteshwar projects, through<br />

two single circuits 6765 KV lines to Meerut for<br />

utilisation in Northern Region.<br />

The esimated cost <strong>of</strong> the entire Tehri Hydro <strong>Power</strong><br />

Complex is Rs. 5058 Crores at December, <strong>1991</strong><br />

price level. An expenditure <strong>of</strong> about Rs. 653 Crores<br />

has been incurred on the project till December, <strong>1991</strong>.<br />

Project Status<br />

• Infrastructure woks completed.<br />

• 4 Nos. diversion tunnels 11 M dia each completed.<br />

• 4 Nos. 8.5 M dia each Head Race Tunnel excavation<br />

completed and lining works is nearing completion.<br />

• Various approach adits to underground <strong>Power</strong> House<br />

cavern completed.<br />

• Foundation work <strong>of</strong> C<strong>of</strong>fer Dam & the Main Dam<br />

have been completed and dam raised to RL. 615<br />

metre throughout its length.<br />

45<br />

PROJECT COST AND COMMISSIONING<br />

SCHEDULE<br />

(Rs. in Crores)<br />

PROJECT ESTIMATED COST COMMISSIONING<br />

(AT DEC., <strong>1991</strong> SCHEDULE<br />

PRICE LEVEL) (PLANNED)<br />

i) Tehri Dam & HPP<br />

(4x250 MW)<br />

2618 1996-97<br />

ii) Koteshwar Dam & HPP<br />

(4x100 MW)<br />

654 1996-97<br />

iii) Tehri Pump Storage<br />

Plant (4x250 MW)<br />

1090 1996-97<br />

iv) Associated Transmission<br />

System (800 KV)<br />

696 1996-97<br />

Total 5058<br />

6.28 NATHPA JHAKRI POWER<br />

CORPORAION LTD. (1500 MW)<br />

Nathpa Jhakri <strong>Power</strong> Corporation (NJPC) was<br />

incorporated on 24th May, 1988 as a Joint Venture <strong>of</strong><br />

Govt. <strong>of</strong> India and Government <strong>of</strong> Himachal Pradesh both<br />

sharing the cost <strong>of</strong> the projects in the ratio <strong>of</strong> 3:1<br />

respectively to plan, promote, organise and execute<br />

Hydroelectric <strong>Power</strong> Projects in the Satluj river basin in<br />

Himachal Pradesh.<br />

NJPC is presently executing its first project Nathpa Jhakri<br />

Hydro-electric Project (Installed Capacity=1500 MW) in<br />

Distt. Kinnaur/Shimla (HP) for which World Bank has<br />

sanctioned a Loan <strong>of</strong> US # 437 million. Besides this<br />

project, NJPC has taken up pre-construction planning <strong>of</strong><br />

Kol Dam Project (I.C. = 800 MW).<br />

Main Features <strong>of</strong> Nathpa Jhakri Project<br />

The Nathpa Jhankri <strong>Power</strong> Project envisages the<br />

construction <strong>of</strong>:<br />

- 60.50 m high concrete dam on Satluj river at Nathpa<br />

to divert 405 cumecs <strong>of</strong> water through four intakes.<br />

- underground desilting complex, comprising four<br />

chambers, each 525 m long, 16.31 m wide and 27.5<br />

m deep, one <strong>of</strong> the largest underground complex in<br />

the World.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!