TECHNICAL SPECIFICATIONS<br />

DENVER INTERNATIONAL AIRPORT<br />

DIVISION 1 – GENERAL REQUIREMENTS<br />

RUNWAY 17R-35L COMPLEX PAVEMENT REHABILITATION<br />

SECTION 01404 – <strong>DIA</strong> QUALITY ASSURANCE FOR FAA FUNDED PROJECTS CONTRACT NO.: 201208806<br />

found to be in nonconformance with contract requirements. When issued, a<br />

nonconformance report will preclude payment for elements noted and will remain in<br />

effect until corrective actions have been submitted, approved and performed.<br />

2. The nonconformance report form will describe the nature and extent of nonconforming<br />

elements and will include space for the Contractor's corrective action proposal, the<br />

designer of record's review of the Contractor's proposal, reinspection and/or verification<br />

of approved corrective rework, and a space for the Project Manager's disposition of the<br />

nonconformance matter. Copies of the Nonconformance Report, at each step of its<br />

processing (i.e., initial issuance to Contractor through final disposition), will be sent to<br />

the Project Manager.<br />

3. The disposition of nonconforming items/materials will be made by the Project Manager.<br />

C. Removal of nonconforming material<br />

1. The Contractor is obligated to correct or remove nonconforming materials, whether in<br />

place or not. If necessary, the Project Manager will send written notification to the<br />

Contractor to correct or remove the defective materials from the project. If the<br />

Contractor fails to respond, the Project Manager may order correction and removal<br />

and/or replacement of defective materials by others, in which case the Contractor shall<br />

bear all costs incurred by such actions.<br />

PART 4 - MEASUREMENT<br />

4.01 METHOD OF MEASUREMENT<br />

A. No separate measurement will be made for work under this Section.<br />

PART 5 - PAYMENT<br />

5.01 METHOD OF PAYMENT<br />

A. No separate payment will be made for work under this Section.<br />

END OF SECTION 01404<br />

ISSUED FOR BID: 11/26/2012 RS&H Revision No. 2012<br />

01404 - 4