18.05.2014 Views

Annual report 2002 - EOI

Annual report 2002 - EOI

Annual report 2002 - EOI

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

DECISIONS FOLLOWING AN INQUIRY 101<br />

1.8 Finally, with regard to the Commission’s argument that the judgement of the Court of<br />

First Instance of 23 September 1994 in case T-461/93 has recognised the independence of<br />

the Community funding procedure from the infringement procedure, the Ombudsman<br />

points out that the independence of the two procedures deduced by the Commission from<br />

this case merely concerns the administrative aspects of these procedures. This judgement<br />

does not put into question the principle according to which the projects, which benefit<br />

from Community funding have to comply with Community law. The Ombudsman therefore<br />

considers that it was irrelevant for the Commission to refer to the above Court case<br />

and to the independence of the two procedures in the framework of the present complaint.<br />

1.9 It appears from the above that, during the period from March 1998 until December<br />

1998, when the Commission’s position on the case changed, the Commission has failed to<br />

provide adequate information, because it concealed from the complainant a fundamental<br />

element in the case, namely that by decision E(98)2297 of 27 July 1998 the Commission<br />

had in the meantime decided to fund under the Cohesion Fund the project which was<br />

subject of the complaint. By doing so, the Commission left the complainant in the belief<br />

that it was still investigating the case. The Commission’s failure to provide the<br />

complainant with adequate information about her case constitutes an instance of maladministration.<br />

The Ombudsman therefore makes the critical remark below.<br />

2 The allegation concerning the reasons why the Commission closed the case<br />

2.1 The complainant alleged that the Commission’s decision to close the case was wrong<br />

in law. The Commission has in fact manipulated the matter and has tried to find means to<br />

close the case, as is shown by the reasoning of the final decision of 20 April 1999. It took<br />

the Commission four years to come to the conclusion that the project predated the entry<br />

into force of Directive 85/337/EEC. However, earlier - on 26 March 1997 and on 19 March<br />

1998 - the Commission proposed including this case as a representative example in<br />

proceedings against Greece for failure to comply with Directive 85/337/EEC.<br />

2.2 In its opinion, the Commission observed that in March 1997 it considered that the<br />

project was launched after the entry into force of Directive 85/337/EEC. It concluded that<br />

the realisation works of the project had commenced before the definitive approval of the<br />

environmental conditions of the project, thus violating the Directive. However, having<br />

obtained new information from the Greek authorities, it informed the complainant in April<br />

1999 that it considered that the project in question was described in the decision of the<br />

Prefecture of Preveza n° 667 of 28 February 1986 which predates the entry into force of<br />

the Directive 85/337/EEC. The Commission considered that this decision approved the<br />

site for the installation of the biological treatment plant, because it contained an annex<br />

with the topographical map of the “Varkas” site. It therefore closed the case.<br />

2.3 The Ombudsman has carefully analysed the documents from the file and from the<br />

Commission’s file inspected on 12 September 2001. From the documents at the disposal<br />

of the Ombudsman, it appears that the chronology of the follow-up of the case is as<br />

follows: On 26 March 1997 (first Commission’s reply to the Committee on Petitions), the<br />

Commission considered that the project had been launched after the entry into force of the<br />

Directive 85/337/EEC. Considering that the works of the project had started before the<br />

definitive approval of the environmental impact assessment, the Commission concluded<br />

that the Directive had been violated. The Commission therefore suggested that this case<br />

would be included in a horizontal proceeding against Greece for infringement of the<br />

Directive. For this reason, the Commission also suspended the funding of the project from<br />

the Cohesion Fund.<br />

2.4 On 19 March 1998 (Commission’s second reply to the Committee on Petitions), the<br />

Commission confirmed the violation of Directive 85/337/EEC and postponed all procedures<br />

relating to the funding of the project. The Commission also confirmed that this case

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!