Annual report 2002 - EOI
Annual report 2002 - EOI
Annual report 2002 - EOI
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
DECISIONS FOLLOWING AN INQUIRY 53<br />
The complainant’s observations on the Commission’s second opinion<br />
The complainant replied to the arguments put forward by the Commission and pointed out<br />
that he had received no suggestion or advice on how to improve the situation. He underlined<br />
that his main disagreement with the Commission related to the amount of personnel<br />
expenditures reflected in their final <strong>report</strong>, and insisted on the fact that the total costs foreseen<br />
in the initial proposal had not suffered any increase.<br />
THE OMBUDSMAN’S EFFORTS TO ACHIEVE A FRIENDLY SOLUTION<br />
After careful consideration of the opinion and observations, the Ombudsman did not<br />
consider that the Commission had responded adequately to the complainant’s claims.<br />
The Commission had justified its request for the reimbursement of part of the expenses,<br />
on the grounds that the complainant’s final financial request was unfounded. In particular,<br />
the institution had taken the view that the increase of the project’s personnel costs without<br />
prior approval from the institution was improper. The Ombudsman noted that on the basis<br />
of point 1.1 of Annex II of the contract (Financial Aspects), the consultant was allowed to<br />
modify the initial project’s estimates, and thus transfer money between different budget<br />
lines.<br />
The Ombudsman’s provisional conclusion was that in the absence of a more convincing<br />
explanation, the reasoning given by the Commission to reject the complainant’s request for<br />
a final payment of his project did not appear to be founded in the rules of the contract. The<br />
Ombudsman therefore proposed that the Commission modify its stand in accordance with<br />
the previous considerations and reconsider the complainant’s request for the final<br />
payment.<br />
The Commission sent its reply in February <strong>2002</strong>. The institution explained that on the<br />
basis of the considerations made by the Ombudsman, it had reviewed the case with a<br />
conciliatory spirit. Taking into account that the contractor had not been given the<br />
Commission’s administrative and financial handbook but only after the signature of the<br />
convention and also that the foreseen aims of the project had been fully achieved, the<br />
Commission expressed its willingness to accept the proposed budgetary changes. A letter<br />
in that regard was to be sent to the contractor.<br />
It pointed out, however, that in a letter of October 2001, the complainant had contested the<br />
ineligibility of some other expenditures. In a reply dated December 2001, the Commission<br />
requested further evidence as regards these dues.<br />
In summary, the Commission agreed to reconsider its request for reimbursement, and to<br />
complete the payment of the project for almost the whole amount foreseen in the contract.<br />
This outcome should only be dependent on the need for the complainant to furnish some<br />
additional evidence.<br />
In his reply to the Commission’s proposal, the complainant welcomed the solution<br />
suggested by the Commission, and agreed to furnish, as many as possible of the requested<br />
documents. The complainant expressed his willingness to do his utmost, so that the best<br />
possible solution could be achieved. He thanked the Ombudsman for the efforts undertaken<br />
on his behalf.<br />
THE DECISION<br />
On the basis of the information gathered in the course of his inquiry, the Ombudsman<br />
concludes that the case has been settled by the European Commission to the complainant’<br />
satisfaction.<br />
Against this background, the European Ombudsman decides therefore to close the case.