68 ANNUAL REPORT | <strong>2002</strong><br />

The ECIP Directing Committee recommended that the Commission consider the project<br />

eligible under action number 3207. This was notified to the complainant by letter of 21<br />

January 1998 which stated that this neither prejudiced the Commission’s formal approval<br />

of the proposal nor constituted a commitment on the part of the Commission. The<br />

Commission’s formal decision was sent on 25 August 1998 together with the Specific<br />

Contract to be signed by the complainant, the Final Beneficiary and the Commission. This<br />

contract contained in annex 2 the provisional budgetary costs presented by the applicant,<br />

namely a total amount of 170 000 €, with a Community co-financing of 50%, namely<br />

85 000 €.<br />

On 24 February 1999, the complainant presented the financial balance for the final<br />

payment. The Commission services evaluated the eligible costs to be 94 415,63 €. On 19<br />

October 2000, the Commission informed the complainant of the result of the financial<br />

evaluation and of the transfer of 4 707,81 € (a first payment had been made and received<br />

on 16 September 1999, for the amount of 42 500 €, namely 50% of the subvention granted<br />

on basis of Facility 1, Article 5 of the contract). This final payment brought the<br />

Commission’s participation to an amount of 47 207,81 €.<br />

On 22 November 2000, the complainant informed the Commission of its disagreement on<br />

the evaluation of the eligible costs, considering that certain costs had unjustifiably been<br />

considered as ineligible. The Commission’s services replied on 30 April 2001 recalling the<br />

rules and procedures of the ECIP programme contained in the specific contract 23 between<br />

the EC and the Final Beneficiary.<br />

On 27 September 2001, considering that the project had been implemented by the<br />

complainant in a satisfactory way, the Commission’s services re-examined certain costs<br />

and re-evaluated the total eligible cost from 94 415,63 € to 101 011,70 €.<br />

Notwithstanding this conciliation effort, the complainant persisted in requesting the reimbursement<br />

of certain costs, which had been judged ineligible, and this on the basis of a<br />

diverging interpretation of the General Conditions’ provisions annexed to the contract.<br />

Afterwards, the complainant informed the Commission that it would bring the matter to<br />

the European Ombudsman.<br />

As regards the complainant’s allegations, the Commission, pointing out the Court of<br />

Justice’s competence to deal with disputes arising from the contract, wished to clarify to<br />

the Ombudsman the legal basis of its action and the arguments on which it based its interpretation:<br />

1 As regards the allegation that its dealing of the file was abnormally long, the<br />

Commission regretted the delays in the treatment of the case. The Commission explained<br />

that these delays were due to the problems encountered in the management of the<br />

programme such as the shortage of personnel and the various internal restructuring procedures,<br />

as well as to the decision to terminate the ECIP programme.<br />

In accordance with its own commitments, the Commission is ready to pay to the Final<br />

Beneficiary the interests for the delay in transferring the subvention amounts, even if this<br />

is not explicitly foreseen in the contract.<br />

2 As regards the allegation concerning the ambiguity of the texts drafted in English, the<br />

Commission observed that by signing the contract, the complainant accepted its terms,<br />

which presupposes that he understood them. The complainant can therefore not a posteriori<br />

invoke the incomprehension of the terms. The Commission services could always<br />

have provided answers to clarification requests or a translation.<br />

23<br />

The specific contract contains the following annexes : the terms of reference (annex 1), the budgetary costs<br />

(annex 2) and the general conditions (annex 3).