Annual report 2002 - EOI
Annual report 2002 - EOI
Annual report 2002 - EOI
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
DECISIONS FOLLOWING AN INQUIRY 51<br />
(i) From March 1998 to February 1999: The final <strong>report</strong> had been sent to the<br />
Commission in March 1998. Its evaluation comprised both its outcome as well as the<br />
financial aspects. It was undertaken by the “Bureau of Technical Assistance” (BAT), which<br />
was managed by Agenor, an independent firm contracted by the Commission. However, in<br />
February 1999, at the end of the contractual relation with Agenor, the Commission did not<br />
renew the contract. The tasks carried out by the BAT could not therefore be completed.<br />
(ii) From May 1999 to January 2000: In order to complete the work previously done by<br />
the BAT, the European Commission set up the CLEO cell, a specific Unit within the<br />
Directorate-General for Education and Culture. This service was only in operation in May<br />
1999, and the evaluation of the complainant’s final <strong>report</strong> was taken up again in June 1999.<br />
Additional information was requested from the contractor in June 1999, to which he<br />
replied by forwarding diverse supportive materials in July, September, October and<br />
November 1999. The Commission still requested further details in December 1999, which<br />
were forwarded on 8 December 1999. Having completed the evaluation of the <strong>report</strong> at the<br />
end of December 1999, the Commission concluded that the financial requests of the<br />
complainant were unfounded and that part of the sums already paid had therefore to be<br />
reimbursed. Accordingly, it launched the appropriate procedures to have this part of the<br />
funding recovered.<br />
As for the Commission’s failure to complete the final payment of the project, the institution<br />
explained that it had filed a first request for reimbursement at the end of January 2000.<br />
Even though this type of request used to be directly sent to the consultants, the procedure<br />
was changed when CLEO took over BAT in March 2000. Under the new scheme, requests<br />
for reimbursement of sums already paid had first to be forwarded to the Commission’s<br />
financial service. Once the authorising officer had agreed, the requests along with the<br />
necessary supportive evidence were transmitted to the Directorate-General Budget, which<br />
is the responsible DG to forward the requests directly to the contractor.<br />
As a result of this cumbersome procedure, the request of reimbursement for an amount of<br />
14.399 € was set at the end of February 2001.<br />
The Commission concluded by refuting the existence of any material damages on the part<br />
of the complainant. Since the delay did not concern a payment, but rather a request for the<br />
reimbursement of sums already paid, the complainant could not claim damages.<br />
The complainant’s observations<br />
In his observations, the complainant considered that the Commission had taken a very<br />
administrative perspective, which did not correspond to the importance of the project and<br />
the efforts all the parties had made for its development.<br />
The complainant explained that the institution had not clearly identified the reasons, which<br />
justified the request for reimbursement. From the information received, he contested the<br />
financial evaluation carried out by the institution, in particular as regards personnel<br />
expenses. At the time the project was set out, in 1995, it was hard to forecast how the work<br />
would unfold. As a result, it had become necessary to increase the amount initially devoted<br />
to personnel at the expense of other budget lines. Nevertheless, the total cost of the project<br />
had remained unchanged. The Commission, on the other hand, never informed the<br />
complainants about the procedure to be followed to change the initial estimates. The<br />
complainant also requested that the request for reimbursement be suspended until the<br />
Ombudsman had taken a decision on this matter.