18.05.2014 Views

Annual report 2002 - EOI

Annual report 2002 - EOI

Annual report 2002 - EOI

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

DECISIONS FOLLOWING AN INQUIRY 51<br />

(i) From March 1998 to February 1999: The final <strong>report</strong> had been sent to the<br />

Commission in March 1998. Its evaluation comprised both its outcome as well as the<br />

financial aspects. It was undertaken by the “Bureau of Technical Assistance” (BAT), which<br />

was managed by Agenor, an independent firm contracted by the Commission. However, in<br />

February 1999, at the end of the contractual relation with Agenor, the Commission did not<br />

renew the contract. The tasks carried out by the BAT could not therefore be completed.<br />

(ii) From May 1999 to January 2000: In order to complete the work previously done by<br />

the BAT, the European Commission set up the CLEO cell, a specific Unit within the<br />

Directorate-General for Education and Culture. This service was only in operation in May<br />

1999, and the evaluation of the complainant’s final <strong>report</strong> was taken up again in June 1999.<br />

Additional information was requested from the contractor in June 1999, to which he<br />

replied by forwarding diverse supportive materials in July, September, October and<br />

November 1999. The Commission still requested further details in December 1999, which<br />

were forwarded on 8 December 1999. Having completed the evaluation of the <strong>report</strong> at the<br />

end of December 1999, the Commission concluded that the financial requests of the<br />

complainant were unfounded and that part of the sums already paid had therefore to be<br />

reimbursed. Accordingly, it launched the appropriate procedures to have this part of the<br />

funding recovered.<br />

As for the Commission’s failure to complete the final payment of the project, the institution<br />

explained that it had filed a first request for reimbursement at the end of January 2000.<br />

Even though this type of request used to be directly sent to the consultants, the procedure<br />

was changed when CLEO took over BAT in March 2000. Under the new scheme, requests<br />

for reimbursement of sums already paid had first to be forwarded to the Commission’s<br />

financial service. Once the authorising officer had agreed, the requests along with the<br />

necessary supportive evidence were transmitted to the Directorate-General Budget, which<br />

is the responsible DG to forward the requests directly to the contractor.<br />

As a result of this cumbersome procedure, the request of reimbursement for an amount of<br />

14.399 € was set at the end of February 2001.<br />

The Commission concluded by refuting the existence of any material damages on the part<br />

of the complainant. Since the delay did not concern a payment, but rather a request for the<br />

reimbursement of sums already paid, the complainant could not claim damages.<br />

The complainant’s observations<br />

In his observations, the complainant considered that the Commission had taken a very<br />

administrative perspective, which did not correspond to the importance of the project and<br />

the efforts all the parties had made for its development.<br />

The complainant explained that the institution had not clearly identified the reasons, which<br />

justified the request for reimbursement. From the information received, he contested the<br />

financial evaluation carried out by the institution, in particular as regards personnel<br />

expenses. At the time the project was set out, in 1995, it was hard to forecast how the work<br />

would unfold. As a result, it had become necessary to increase the amount initially devoted<br />

to personnel at the expense of other budget lines. Nevertheless, the total cost of the project<br />

had remained unchanged. The Commission, on the other hand, never informed the<br />

complainants about the procedure to be followed to change the initial estimates. The<br />

complainant also requested that the request for reimbursement be suspended until the<br />

Ombudsman had taken a decision on this matter.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!