Electric Power Outlook - Pennsylvania Public Utility Commission
Electric Power Outlook - Pennsylvania Public Utility Commission
Electric Power Outlook - Pennsylvania Public Utility Commission
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Ohio, <strong>Pennsylvania</strong>, Tennessee, Virginia, West Virginia and the District of Columbia. See Figure<br />
3.<br />
Figure 3 PJM RTO service territory<br />
On April 1, 2002, PJM West became<br />
operational, broadening the regional scope of<br />
the electric grid operator for the Mid-Atlantic<br />
Region, to include Allegheny <strong>Power</strong> and<br />
marking the first time, nationally, that two<br />
separate control areas were operated under a<br />
single energy market and a single governance<br />
structure.<br />
On May 1, 2004, PJM began managing the flow<br />
of wholesale electricity over Commonwealth<br />
Edison’s 5,000 miles of transmission lines in<br />
Illinois, making PJM the world’s largest grid<br />
operator, meeting a peak demand of 87,000 MW. On Oct. 1, 2004, PJM began managing<br />
American <strong>Electric</strong> <strong>Power</strong>’s (AEP) eastern control area, including 22,300 miles of high-voltage<br />
transmission lines within a seven-state area and 23,800 MW of generating capacity. At the same<br />
time, Dayton <strong>Power</strong> and Light integrated into the PJM RTO with 1,000 miles of transmission lines<br />
and 4,450 MW of generation. Also, 20 municipal electric companies, cooperatives and generators<br />
in the AEP area joined PJM. On Jan. 1, 2005, PJM began managing the wholesale flow of<br />
electricity for Duquesne Light Company, with 3,400 MW of capacity and 620 miles of<br />
transmission lines. These entities, including Allegheny, comprise PJM West.<br />
Virginia <strong>Electric</strong> and <strong>Power</strong> (Dominion) was integrated into the PJM RTO on May 1, 2005.<br />
Dominion’s control area, covering parts of Virginia and North Carolina, operates separately under<br />
the single PJM energy market as PJM South, including an additional 6,100 miles of transmission<br />
lines and 26,500 MW of generating capacity.<br />
On Aug. 17, 2009, FirstEnergy Service Company filed a request with FERC to consolidate all of<br />
its ATSI 14 transmission assets, currently operated by MISO, into the PJM RTO. ATSI has 32<br />
interconnections with PJM, but only three with MISO. Moving ATSI into the PJM RTO is<br />
expected to reduce congestion and increase efficiency across both RTOs. The integration, which<br />
was approved by FERC on Dec. 17, 2009, became effective June 1, 2011.<br />
On May 20, 2010, Duke Energy Corporation announced its desire to move its Ohio and Kentucky<br />
utilities from MISO to the PJM RTO by Jan.1, 2012, which would increase PJM’s generating<br />
capacity by 2,379 MW. The subsidiaries would also add 5,800 MW to PJM’s system peak load.<br />
14 American Transmission Systems Inc., a subsidiary of FirstEnergy Corporation, has assets located within the footprint<br />
of FirstEnergy’s Ohio and <strong>Pennsylvania</strong> (Penn <strong>Power</strong>) utilities, including 7,100 circuit miles of transmission lines with<br />
nominal voltages of 345 kV, 138 kV and 69 kV.<br />
6<br />
<strong>Pennsylvania</strong> <strong>Public</strong> <strong>Utility</strong> <strong>Commission</strong>