04.06.2014 Views

Electric Power Outlook - Pennsylvania Public Utility Commission

Electric Power Outlook - Pennsylvania Public Utility Commission

Electric Power Outlook - Pennsylvania Public Utility Commission

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Based on forecast growth data, consumption reduction goals total 1.5 million MWh in 2011 and<br />

4.4 million MWh in 2013. Peak demand reduction goals total 1,193 MW for 2013. These goals<br />

were adopted by the <strong>Commission</strong> on March 26, 2009. Total program costs are estimated at just<br />

under $1 billion. 35 See Table 3.<br />

Table 3 Consumption and peak demand reduction goals and cost<br />

Company 1% (MWh) 3% (MWh) 4.5% (MW) Total Plan Cost<br />

Duquesne 140,855 422,565 113 $78,183,806<br />

Met-Ed 148,650 445,951 119 $99,467,568<br />

Penelec 143,993 431,979 108 $91,898,976<br />

Penn <strong>Power</strong> 47,729 143,188 44 $26,639,136<br />

PPL 382,144 1,146,431 297 $246,005,504<br />

PECO 393,860 1,181,580 355 $341,580,634<br />

West Penn 209,387 628,160 157 $94,249,872<br />

Total 1,466,618 4,399,854 1,193 $978,025,496<br />

In 2009, the <strong>Commission</strong> established standards each program must meet and provided guidance on<br />

the procedures to be followed for submittal, review and approval of all aspects of EDC plans.<br />

Programs are evaluated using a total resource cost test. 36 Each plan must include a proposed cost<br />

recovery tariff mechanism. Plans were filed on July 1, 2009. 37 The <strong>Commission</strong> approved the<br />

plans, with modifications, in late October 2009, requiring the filing of revised plans within 60<br />

days, which were subsequently approved. 38<br />

Smart Meters and Time-of-Use Rates<br />

39<br />

Section 2807(f) of the <strong>Public</strong> <strong>Utility</strong> Code requires that EDCs, with greater than 100,000<br />

customers, file a smart meter technology procurement and installation plan with the <strong>Commission</strong><br />

for approval. Smart meters are to be furnished upon request from a customer that agrees to pay the<br />

cost of the meter, in new building construction, and in accordance with a depreciation schedule not<br />

to exceed 15 years.<br />

A Smart Meter Procurement and Installation Implementation Order was adopted by the<br />

40<br />

<strong>Commission</strong> on June 18, 2009. Each smart meter plan must include a summary of the EDC’s<br />

current deployment of smart meter technology, if any; a plan for future deployment complete with<br />

dates for key milestones; and measurable goals and other pertinent information. The <strong>Commission</strong><br />

granted a network development and installation grace period of up to 30 months following plan<br />

35 Program costs are from individual plans and generally represent 2 percent of revenues as of December 2006<br />

multiplied by four to reflect the four-year duration of the plans.<br />

36 Docket No. M-2009-2108601.<br />

37 Docket No. M-2008-2069887.<br />

38 Docket Nos. M-2009-2093215, M-2009-2093216, M-2009-2093217, M-2009-2093218, M-2009-2092222, M-2009-<br />

2112952 and M-2009-2112956.<br />

39 66 Pa. C.S. § 2807(f).<br />

40 Docket No. M-2009-209655.<br />

18<br />

<strong>Pennsylvania</strong> <strong>Public</strong> <strong>Utility</strong> <strong>Commission</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!