Figure 5 Mid-Atlantic Area National Corridor and Critical Congestion Area<br />
On Jan. 28, 2010, the <strong>Commission</strong> issued a Tentative Order 20 which sets forth specific Interim<br />
Guidelines to supplement the existing filing requirements, pending the conclusion of the<br />
rulemaking process. The additional information to be included in the initial filing is intended to<br />
streamline the application process by reducing the need for subsequent data requests, on a case-bycase<br />
basis, to more completely develop the record necessary to process the application. Comments<br />
to the Tentative Order were filed in March 2010.<br />
In recent transmission line siting proceedings, the <strong>Commission</strong> has given substantial weight to<br />
regional transmission studies conducted by PJM.<br />
The PJM Regional Transmission Expansion Plan (RTEP) identifies transmission system upgrades<br />
and enhancements to preserve grid reliability within the region, the foundation of competitive<br />
wholesale power markets. The RTEP five-year planning process enables PJM to assess and<br />
recommend transmission upgrades to meet forecasted near-term load growth and to ensure the safe<br />
20 Docket No. M-2009-2141293; 40 Pa.B. 953.<br />