ATLAS # 43734 - Terra Santa School<br />
Construction <strong>of</strong> Multi-Purpose Hall and finishing works at the Basement in the Terra Santa Kindergarten<br />
Item# Description Unit Qty. Rate Amount<br />
(<strong>Bill</strong> - 11 ) ELECTRICAL WORKS<br />
11 a) Preamble:<br />
All electrical works shall be according to general and particular<br />
specifications, drawings, engineer’s approval, complete ready for<br />
work in place and in operable manner including chipping in walls,<br />
excavation, backfilling , cutting, fixing, cables ,conduits ,pipes ,<br />
testing and handling over to JERUSALEM Electric Authority. The<br />
contractor should hold any test required according to supervisor<br />
engineers approval.<br />
11.01 Supply, install, fix, connect , commission ,label and test the<br />
following final distribution panel boards (Metal) including LV<br />
section, Legrand or equally approved circuit breakers, pipes and<br />
all components, ready for work according to drawings,<br />
specifications and engineer’s approval.<br />
11.01.1 DB-HALL No 1<br />
11.01.2 DB-KVAR (80KVA) complete ready for work. No 1<br />
11.02 Supply, install, connecting, commission and testing the following<br />
items including conduits, conduit accessories, boxes, wires,<br />
switches, cables, socket outlet devices and all what is necessary<br />
according to drawings, specifications and engineer’s approval. ,<br />
Legrand or equally approved.<br />
11.02.1 Light point. No 175<br />
11.02.2 6A 3 pins with automatic shutter socket outlet. No 3<br />
11.02.3 16A 3 pins with automatic shutter power socket outlet fot th e No 2<br />
Split unit use, with double pole switch and sign lamp.<br />
11.02.4 6A 3 pins (WP) Twin socket outlet with automatic shutter. No 3<br />
11.02.5 16A 3 pins with automatic shutter Twin socket outlet No 18<br />
11.02.6 Ditto as item (e)but Modular flush mounted floor service outlet No 3<br />
box in the stage<br />
11.02.7 Hand Dryer point. No 2<br />
11.02.8 Double pole switch with indicating lamp. No 2<br />
11.02.9 Photocell activated Hand Dryer (2000W)-Venta. No 2<br />
11.02.10 Extract fan point. No 4<br />
11.03 Supply, install, connect ,commission and testing the following<br />
lighting fixtures including tubes, starters, capacitors, ballasts,<br />
bulbs, and all what is necessary according to drawings,<br />
specifications and engineer’s approval .GAASH or equally<br />
approved.<br />
11.03.1 4x18W fluorescent lighting fixture with double parabolic reflector- No 86<br />
false ceiling mounted.<br />
11.03.2 2x18W-PL (W.P) fixture with opal cover ceiling mounted. No 17<br />
11.03.3 2x8 W 3 hours duration non – maintained emergency lighting<br />
fixture.<br />
No 15<br />
11.03.4 As above but EXIT light. No 5<br />
11.03.5 Spot lights – Halogen (50W).in falser ceiling. No 20<br />
11.03.6 Wall mounted (60W globe) - WP. No 5<br />
11.03.7 Projection lights-100W on metal support complete. No 9<br />
11.03.8 Hexagonal lantern-60W wall mounted. No 6<br />
11.03.9 1*36W) Fluorescent lighting fixture with U reflector. No 6<br />
Consultant: Diyar Consultants Co. Engeering Unit @ <strong>UNDP</strong>/PAPP 15/31