$5.5 million transformation:<br />

The Rober<br />

obert t C. Walter <strong>St</strong>udent Commons and<br />

the <strong>St</strong>udent Services & Fine Arts Center<br />

A new architectural sketch of what the main <strong>St</strong>. <strong>Charles</strong><br />

school building will look like after construction of the<br />

Robert C. Walter <strong>St</strong>udent Commons and the <strong>St</strong>udent<br />

Services & Fine Arts Center is completed next spring.<br />

This was the scene in mid-July when demolition was<br />

begun on the original powerhouse and remains of its<br />

smokestack at <strong>St</strong>. <strong>Charles</strong>.<br />

A crane is worked carefully to take down a school<br />

landmark, the remains of the powerhouse smokestack.<br />

By late August, digging footers for Walter Commons<br />

was almost completed and the foundation of a future<br />

stage had taken shape.<br />

Excavating machines create a huge crater for part of the<br />

foundation of the <strong>St</strong>udents Services & Fine Arts Center.<br />

The basement of the former powerhouse is being<br />

modified and expanded in conjunction with the new<br />

construction.<br />

In early October, three-quarters of the concrete for the<br />

floor of the Walter <strong>St</strong>udent Commons had been poured.<br />

Upon the completion of backfilling various locations,<br />

work was set to begin on the steel skeleton for the<br />

<strong>St</strong>udents Services & Fine Arts Center<br />

A concrete pumper boom truck just finishes pouring the<br />

basement floors of the <strong>St</strong>udent Services & Fine Arts<br />

Center. The brick tower had been topped off a day earlier<br />

and steel beams were being erected in the first week of<br />

November.<br />

Cold winter weather has not slowed down progress.<br />

The Distinctive Leader in Catholic Education<br />