Changing Policy: The Navy currently requires the standard AP format outline in the ASN (RD&A) Planning<br />
Guide to be used. However, the Navy Acquisition Procedures Supplement (NAPS) is being revised to state that no<br />
strict AP format is necessary, provided the requirements of FAR 7.104 and 7.105 are generally met and the MDA<br />
concurs. Contact the POC below before writing your Acquisition Plan as this change should be in effect shortly.<br />
Review & Approval: Once completed and approved by the IPT, the AP is submitted for signature of the program<br />
manager, contracting officer, and the Head of Contracting and then forwarded it to the cognizant PEO or AIR-1.0<br />
(for NAVAIR programs) for final approval.<br />
Revisions: The program manager should review the AP annually to see if a revision is necessary. Specific<br />
guidance on what constitutes a revision is provided in paragraph 10 of NAVAIRINST 4200.36. An AP revision<br />
may be forwarded for approval in memorandum format explaining the nature of the change(s) and will include as<br />
an enclosure those pages of the original AP that have been changed. The changed parts will be indicated by a<br />
vertical line in the margin and a date in the upper right hand corner. An approval signature page, similar to the<br />
one on the original AP, will be used for AP updates. The signature page is signed by the same review codes and<br />
approval authority as the original AP. Review of the revision is to be confined to those review codes responsible<br />
for or effected by the particular functional areas being changed. If the extent of the changes requires a complete<br />
rewrite, an entirely new AP will need to be written. See NAVAIRINST 4200.36 for additional details.<br />
Lessons Learned:<br />
1) The AP should reflect a minimum of three years of program effort. The signature page should state the<br />
contract years which are covered by the AP and when (FY or milestone) the next revision is planned for or<br />
anticipated.<br />
2) The use of past performance as a source selection factor should be cited, when applicable, in the AP. It can be<br />
mentioned in standard paragraphs of the AP format that deal with proposed sources and basis for selection,<br />
competition, source selection procedures, other contract/business considerations, and risks.<br />
3) Be sure to have an approved Acquisition Strategy for an ACAT program prior to submitting the AP for final<br />
approval. The AP cannot be approved without it. Ensure their is no conflicting information between the AP and<br />
the Acquisition Strategy. For some programs, particularly those for which the PEO and MDA are the same<br />
(ACAT III and IV), the Acquisition Strategy and AP may be combined into one document<br />
POC: Tom Dewland, AIR-1.1B, room 354, bldg 2272, (301)757-6623<br />
Jackie Mercer, AIR-1.1C, room 354, bldg 2272, (301) 757-6624<br />