If hazardous materials are required <strong>for</strong> any un<strong>for</strong>eseen reason, a hazardous waste<br />
management plan would be prepared. The plan will detail terms applying to the purchase,<br />
storage, use, handling and disposal of such materials.<br />
The impact of hazardous materials will be minimised through a range of control measures<br />
including, but not limited to, those outlined below.<br />
Hazardous materials will be properly classified and managed in accordance with<br />
requirements <strong>for</strong> their particular class.<br />
An evaluation of alternative materials will be undertaken be<strong>for</strong>e use of chemicals is<br />
approved.<br />
Hazardous materials will be transported, stored and used in accordance with the<br />
corresponding material safety data sheets which will be available on the site.<br />
Hazardous materials will be stored in a locked and bundled area at the site; incompatible<br />
chemicals will not be stored together.<br />
No fuels will be stored on site. Refuelling will be undertaken at off-site facilities.<br />
Adequate spill prevention, containment and response measures (e.g. drip trays) will be<br />
provided on site if needed.<br />
Construction personnel will be trained in spill containment and response procedures.<br />
All storage and handling equipment on site will be maintained properly.<br />
4.10 Visual Aesthetics and Urban Design<br />
Existing Situation<br />
The visual landscape surrounding the proposed site includes the South Coast Line and<br />
associated overhead power lines. There is vegetation surrounding the corridor largely<br />
associated with the Illawarra Conservation Area to the west.<br />
Residential dwellings are about 220 metres east from Location 1 and about 420 metres east<br />
from Location 2 on Railway Crescent.<br />
Potential Impacts<br />
During construction the visual environment will be temporarily altered through the presence of<br />
temporary work buildings, plant and equipment.<br />
While the site is operational, a new 10 metre high tilted mast will be introduced into the visual<br />
environment. The 1.7 metre high cabinet and a small mast mounted on west end of portal will<br />
be of little visual significance.<br />
A photomontage of the new hinged mast and portal mounted mast is provided as a guide in<br />
Figure 5 and Figure 6..<br />
Page 44 of 72