25.04.2015 Views

Part 1 - Palmerston North City Council

Part 1 - Palmerston North City Council

Part 1 - Palmerston North City Council

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

gemconsulting<br />

same as the upstream end of the rock lining) and will be constructed to a height that corresponds with the<br />

annual return flood level.<br />

Temporary Cofferdam<br />

A cofferdam will be constructed from the snub groyne to the temporary river channel to divert the river<br />

into the channel and thereby allowing construction of the rock lining to proceed in a flow free river bed. A<br />

further cofferdam will be constructed at the downstream end of the works to prevent water back‐flowing<br />

into the work area and to minimise sediment release form the works to the river.<br />

Rock Lining<br />

Rock linings generally provide protection against lateral erosion through the placement of rock directly<br />

against the lower sections of the river bank.<br />

In this instance the rock lining will be constructed away from the base of the cliff and will be reinforced by<br />

the gravel previously stockpiled in the middle of the river by placing it behind the rock lining as the work<br />

progresses. The lining will have a similar design to other rock linings already constructed within the <strong>City</strong><br />

Reach. It will be approximately 460 metres long. The rock lining will extend one metre below the level of<br />

the river bed when the works are complete with the upper level of the lining at a height corresponding with<br />

the annual return flood level. The lower part of the lining will be constructed with a median rock size of<br />

750kg and be 1.7 metres thick. Above this, the lining will be constructed with a median rock size of 300kg<br />

and will be 1.2 metres thick. The whole lining will have a 2:1 slope (26.6 degrees).<br />

The rock lining will be constructed to allow the unnamed tributary to enter the Manawatu River with the<br />

top part of the wall curving towards the stream as shown on Figure 1 (attached as Appendix B). The stream<br />

will be channelled across the gravel backfill and through this ‘gap’ in the rock lining.<br />

As mentioned, PMB Landco Ltd intends to re‐contour the western cliff. These works will see the cliff<br />

battered back to a slope starting from a point that leaves a seven metre wide bench on the rock lining to<br />

allow access for maintenance of the lining and for a possible future walkway connecting ANZAC Park to Pari<br />

Reserve. The lower part of the re‐contoured cliff will be lined with quarry rock to protect the fine soils from<br />

the cliff being eroded during floods that are higher than the annual return flood level.<br />

Bed Armouring<br />

Bed armouring layers consist of a few widely spaced larger rocks interspersed with smaller rocks. The larger<br />

rocks reduce the flow velocity close to the river bed thereby minimising scouring. The bed armouring<br />

concept has been successfully used in two locations within the <strong>City</strong> Reach; around the groynes at Fitzroy<br />

Bend and at the downstream end of the Katene Street rock lining.<br />

The new bed of the river will be armoured to prevent any scouring that may undermine the new rock lining.<br />

This armouring layer will be 500mm thick and consist of 80% reject quarry rock and 20% rock with a 300kg<br />

median weight.<br />

Gravel Recovery (if required)<br />

There is a risk that if a flood occurs during the construction period it could potentially wash stockpiled<br />

gravels downstream. If this occurs, recovery of these gravels will likely be required to ensure enough gravel<br />

is available to support the rock lining and complete the works.<br />

Tied Tree Works<br />

Once the rock lining is completed, the river bank upstream of the lining will be protected with tied tree<br />

works. The purpose of this activity is to prevent lateral erosion of the river bank and maintain river<br />

alignment, by providing relatively heavy vegetative protection, developing strong root systems, and<br />

encouraging the deposition of sediment at the toe of the banks. The works will involve anchoring live trees<br />

to the river bed and bank with wire ropes and anchors. Further tree planting will be carried out behind the<br />

tie tree works during the winter following construction.<br />

6

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!