CDOP-2 <strong>Project</strong> <strong>Plan</strong><br />
(<strong>Main</strong>)<br />
Doc. No: <strong>SAF</strong>/H<strong>SAF</strong>/<strong>CDOP2</strong>/PP/1.0<br />
Issue: Version 1.0<br />
Date: 11/12/2012<br />
Page: 26/99<br />
470<br />
480<br />
490<br />
500<br />
510<br />
Costs Report). The document acts as the monitoring tool in which clear evidence will be given on the<br />
status and progress of the <strong>Project</strong>’s WPs at a given cut off: WPs’ percentage of completion, Man<br />
Power effort accounting, other costs accounting shall be some of the information included in the<br />
report.<br />
The <strong>Project</strong> Status Report will be regularly updated and delivered twice a year, shortly before the<br />
scheduled Steering Group meetings; and will be presented to SG for consideration and<br />
endorsement.<br />
The Financial Report (Assets and Costs Report) will be delivered once a year: a preliminary release is<br />
foreseen at the end of the year, the final release is scheduled in the first quarter of each year.<br />
2.3.4 Engineering<br />
Within Support Functions (see 2.4.2), Engineering Management provides general coordination of the<br />
engineering activities that take place at the various product generation centres.<br />
It provides guidance aiming at harmonising the engineering procedures applied by the product<br />
generation centres, with special emphasis on the implementation of user-friendly standard codes<br />
and formats.<br />
It includes, moreover, the activities of verification and regression testing necessary to ensure correct<br />
integration of new or improved algorithms into the operational chains.<br />
This task provides the engineering documentation needed for the Review meetings. Configuration<br />
management activities, described in section 2.3.7.2, are also coordinated by the Engineering<br />
Management.<br />
The WP, as shown in RAM (see 2.4.2), is responsibility of Telespazio.<br />
2.3.5 Science Management<br />
Science Management is responsible for the coordination of scientific aspects of H-<strong>SAF</strong> during CDOP-<br />
2, among which the supervision of scientific tasks related to continuous development,<br />
hydrovalidation and product validation.<br />
It takes care of the revision of all scientific documents delivered and/or maintained during CDOP-2<br />
and is responsible of the contacts with all participants as far as scientific matters are concerned.<br />
This task controls the product requirements verifying the compliance with the user requirements.<br />
Visiting Scientist activities coordination and management is also a prerogative task of the Science<br />
Management.<br />
The Scientific Coordination is in charge of the Science Manager, who attends to relevant meetings<br />
when the case, at <strong>SAF</strong> Network level<br />
The Science Manager will also accomplish to the settlement and running of the H-<strong>SAF</strong> Algorithm<br />
Group and H-<strong>SAF</strong> Soil Moisture & Snow Scientific Advisory Group.<br />
Algorithm Group:<br />
The H-<strong>SAF</strong> Algorithm Group is a working group set up during CDOP with the aim of having<br />
represented the knowledge on algorithm for the H-<strong>SAF</strong> products. Members are chosen among<br />
Cluster Leaders, Responsible of Generation Chains or Responsible of product development. The<br />
Group is under the coordination of the Science Manager, and have organized an Algorithm and<br />
Validation Forum for each production cluster with the aim of discussing on the algorithms, their<br />
maturity, their potential evolution, and their associated validation,.<br />
Soil Moisture & Snow Scientific Advisory Group