8.8 Outline information required for <strong>SuDS</strong> evaluation<br />
8.8.1<br />
The information required at Outline <strong>Design</strong> The Outline <strong>SuDS</strong> <strong>Design</strong> will show what the<br />
stage will depend on whether a Concept scheme will look like, how it will function and<br />
<strong>Design</strong> has been provided and the level of confirm any additional information provided<br />
information included at that stage.<br />
since Concept <strong>Design</strong> Stage.<br />
The design information should be provided in<br />
plan form, confirming site layout and <strong>SuDS</strong><br />
infrastructure together with a <strong>SuDS</strong> <strong>Design</strong><br />
Statement presenting all information that<br />
cannot be conveyed on plan.<br />
Outline <strong>Design</strong><br />
8.8.2 Outline <strong>Design</strong> – information checklist<br />
Information recommended in the LASOO (Local<br />
Authority <strong>SuDS</strong> Officer Organisation) Practical Guidance<br />
■■<br />
Flood Risk Assessment (FRA) – a review<br />
■■<br />
ground investigation review<br />
of critical elements<br />
■■<br />
evidence of third party agreement for<br />
■■<br />
■■<br />
Outline <strong>Design</strong> Strategy Statement<br />
Outline <strong>Design</strong> Plan – layout<br />
consent to discharge or agreement in<br />
principle.<br />
64<br />
■■<br />
the plan will incorporate preliminary<br />
landscape proposals<br />
Additional information to inform evaluation of the scheme:<br />
■■<br />
topographical information and flow route<br />
■■<br />
sensitive receptors for runoff where<br />
analysis<br />
appropriate e.g. SSSIs<br />
■■<br />
destination and discharge route of rainfall<br />
■■<br />
offsite works that may be required<br />
via infiltration or runoff<br />
■■<br />
general maintenance principles<br />
■■<br />
infiltration investigation results where<br />
appropriate<br />
■■<br />
design life of any products used and<br />
requirements for potential replacement.<br />
■■<br />
existing utilities plan confirming existing<br />
watercourses or sewer locations<br />
London Borough of <strong>Hillingdon</strong> <strong>SuDS</strong> D & E <strong>Guide</strong><br />