18.03.2021 Views

Insight 2017

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Michaelmas <strong>2017</strong> 12<br />

the garden and the new private lodgings from the west<br />

(Library) end. Most importantly, the new roof light and all<br />

interventions are invisible in the long view to the west<br />

elevation and statues of the existing Library.<br />

Queen’s with a number of opportunities to reconfigure and<br />

extend for future use.<br />

The build<br />

Construction of the new building commenced in spring 2015<br />

and ran for 89 weeks through two kind winters completing in<br />

spring <strong>2017</strong>.<br />

The main contractor, Beard, are a very experienced and skilled<br />

local company with a great deal of experience working in<br />

collegiate Oxford – and specifically at Queen’s, having<br />

completed the kitchen project in 2009. Their expertise and<br />

familiarity assisted in the two major challenges of the build:<br />

getting material to and from the site and digging a large hole<br />

that was both very close to and beneath existing historic listed<br />

structures.<br />

View of the new garden from the Provost’s Lodgings—looking toward the<br />

library<br />

The garden provides two terraces, a circuit of paths and a<br />

variety of new beds and space for a vegetable garden and new<br />

garden store. The paths and ramps make all areas of the<br />

garden accessible to wheelchair users. The below ground<br />

structure and overall garden design has been carefully<br />

configured to safeguard the existing magnificent copper beech<br />

tree which has been carefully protected throughout and we are<br />

pleased to say is prospering in its new setting.<br />

The challenge of building close to existing structures involved<br />

much careful design<br />

work, as well as<br />

buildability studies<br />

being carried out by<br />

the design team<br />

before the project got<br />

to site. Regular<br />

movement checking<br />

was completed in<br />

advance of going on<br />

site to ensure no<br />

damaging movement<br />

of the existing walls,<br />

Library or Lodgings<br />

was taking place.<br />

The forming of the<br />

piles and internal<br />

concrete box was a<br />

careful and steady<br />

process of piling, The new basement level in its early stages<br />

digging, supporting,<br />

backfilling, bracing and finally - with the lid - forming a rigid<br />

waterproof concrete box. The careful iterative process of<br />

building in-the-ground was particularly acute in forming the<br />

link between the new building and Lower Library, where a<br />

bespoke design was used to tunnel beneath the existing<br />

Library footings forming a new basement 5m below the<br />

functioning Library.<br />

Aerial view of the construction site where the garden was replanted<br />

Fitting out the building<br />

Choosing fixtures and fittings for a building is always an added<br />

pleasure for architects and we have greatly enjoyed being<br />

involved in designing the tables, insignias, manifestations, and<br />

fixed furniture together with selecting the new reading chairs,<br />

and other details.<br />

Elsewhere<br />

Benefitting the wider College, the project frees-up 4500sqft for<br />

reuse. Liberated spaces include an extensive basement and<br />

above ground spaces on Front and Back Quad providing<br />

The waterproof box was completed with the installation of 4<br />

super-sized frameless glass roof lights along the eastern edge.<br />

These enormous pieces were carefully manoeuvered into place<br />

by a number of cranes and small lifting machines in early <strong>2017</strong><br />

to finally seal the new building.<br />

The fit-out of the building was no less complex than the<br />

structural works with extensive special fittings to be concealed<br />

and accommodated. The invisibility of air-conditioning,<br />

heating and other services is the result of careful coordination<br />

between joinery and environmental design where the new<br />

shelving often straddles low-level ducts, and grilles. At the top<br />

of shelves, extract ventilation occurs together with much of

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!