Major Construction in Full Stream<br />
Implementation of Stage 1 Traffic Management Scheme by end <strong>2011</strong><br />
Construction of the <strong>Kwun</strong> <strong>Tong</strong> <strong>Line</strong> <strong>Extension</strong> (KTE) has been proceeding smoothly since last May. Site formation at Ho Man Tin<br />
Station and the utilities diversion at Whampoa have been substantially completed. Excavation at Ho Man Tin Station is underway. The<br />
Temporary Traffic Management Scheme (TTMS) for the cut-and-cover works at Whampoa, including temporary closure of traffic lanes<br />
at Tak On Street and relocation of the Green Mini Bus (GMB) and other bus stops, will be implemented in end <strong>2011</strong>.<br />
Project Progress<br />
Ho Man Tin Station<br />
<strong>December</strong> <strong>2011</strong><br />
• The removal of trees in the Ho Man Tin Station site is in progress since<br />
November after approval by the Lands Department. Inspections have been<br />
conducted by tree experts in which the health conditions, height, species and<br />
safety factors were properly recorded prior to the works. It is recommended<br />
that trees with a low survival rate after transplanting are to be removed, while<br />
some will be planted on the slopes adjacent to the station as compensation,<br />
which will result in a larger number of trees in total.<br />
• Wuhu Street Temporary Playground will be temporarily closed from March<br />
2012 to facilitate the construction of the new covered footbridge across<br />
Chatham Road North.<br />
• The kerosene station at Chung Hau Street will be demolished to make way for<br />
the construction of the station entrance and public transport interchange.<br />
• Works on the construction shaft and noise<br />
enclosure at Fat Kwong Street Playground<br />
is in progress. The noise enclosure will<br />
effectively help reduce the noise of<br />
construction of the shaft, thus minimising<br />
nuisance to the residents nearby.<br />
• Excavation is being carried out for the Ho Man Tin Station. Open blast for the construction of station and relevant facilities will be<br />
carried out in early 2012 when the excavation reaches the required depth to hard rock.<br />
Whampoa Station<br />
• Man Siu Street has been permanently<br />
closed since September <strong>2011</strong>. Meanwhile,<br />
the footbridge connecting Man Siu<br />
Street and Site 11 of Whampoa Garden is<br />
temporarily closed until 2015 for staircase<br />
modification and pipe pile installation.<br />
• Pipe pile works at the junction of Hung Hom<br />
Road and Tak Man Street is in progress. The<br />
dividing strip between the traffic lanes at<br />
Hung Hom Road has also been demolished<br />
for road modification works.<br />
• Underground utility diversion and road modification is<br />
in progress at the junction of Tak On Street and Shung<br />
King Street for construction of the station concourse<br />
by the cut-and-cover method. It is expected to be<br />
completed by end <strong>2011</strong>.<br />
• Road modification works at Wan Hoi Street has been<br />
completed. Erection of hoardings and the construction<br />
of the shaft and noise enclosure are underway.