20.03.2013 Views

TUNNEL ENGINEERING

TUNNEL ENGINEERING

TUNNEL ENGINEERING

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Fig. 20.9 Tangent Piles.<br />

deep. The ease and simplicity of constructing the<br />

final structure within temporary walls must be<br />

balanced against cost savings when they are<br />

incorporated into the final structure. Temporary<br />

excavation support may be steel sheet piles, soldier<br />

piles and lagging, and tangent or secant piles. For<br />

deeper excavations, concrete slurry walls may be<br />

constructed, usually 2 ft, 3 ft, or 4 ft thick, sometimes<br />

incorporating soldier piles or beams (SPTC<br />

walls), and may form part of the final structure.<br />

Steel sheetpile walls, for depths to about 30 to<br />

40 ft, supported by wales and cross bracing. The<br />

walls keep loss of ground to a minimum.<br />

Soldier piles and lagging, made of steel H<br />

beams with wood or concrete lagging. These are<br />

used for greater depth. Lagging must be blocked<br />

tight against the earth to control loss of ground.<br />

Soldier piles may be combined with sheetpiles,<br />

instead of wood lagging, if tight bulkheads are<br />

required. Wales and cross bracing support the<br />

walls.<br />

Concrete slurry walls built in bentonite-slurry<br />

trenches have been used to prevent loss of ground<br />

<strong>TUNNEL</strong> <strong>ENGINEERING</strong><br />

Tunnel Engineering n 20.21<br />

and eliminate or reduce groundwater lowering.<br />

Sections of trenches about 20 ft long are excavated.<br />

The trenches are kept filled with bentonite slurry.<br />

Then, reinforcing cages are lowered into them, and<br />

concrete is placed to fill the trenches, displacing the<br />

slurry. Key sections are formed at the ends of the<br />

trenches. The walls serve as part of the final<br />

structure or as impervious bulkheads.<br />

SPTC or California Wall, a combination of<br />

soldier piles and slurry wall. This was used on<br />

some stations of BART, and as part of the final<br />

structure for much of the Central Artery Project in<br />

Boston. Large wide-flange steel beams are inserted<br />

in slurry-filled bored holes, the space between the<br />

beams is excavated under slurry, and excavation<br />

and pipe holes are filled with concrete. Care must<br />

be used in excavation to have the concrete solidly<br />

keyed into the space between the flanges. The steel<br />

piles in the composite wall act as reinforcing and<br />

permit easy attachment of interior bracing.<br />

The fundamental basis for the design of<br />

excavation support systems is consideration of<br />

how the soil being supported behaves, and perhaps<br />

also how the floor of the trench behaves, since<br />

substantial heave can occur under adverse conditions.<br />

Any movement of the support system can<br />

cause soil movement and hence settlement of<br />

adjacent structures. It is the amount of movement<br />

that can be tolerated at the adjacent structures that<br />

often dictates the type and stiffness of the<br />

excavation support system, with control of<br />

ground-water levels often being crucial. Structures<br />

may have to be designed for both short-term and<br />

long-term effects. One of the primary tools for<br />

this purpose is soil-structure interaction analysis.<br />

Frame structures supported by beam-on-anelastic-foundation<br />

analysis are also commonly<br />

used. In most cases, a two-dimensional analysis is<br />

sufficient, although complex areas may require<br />

three-dimensional modeling, perhaps using finite<br />

element analysis.<br />

Many subway and highway structures have<br />

been built using steel columns and beams with jack<br />

arches, but this is uncommon today. New structures<br />

are generally reinforced concrete box structures<br />

but when the excavation support system also<br />

forms part of the final structure, it may in practice<br />

be difficult to obtain full fixity between the walls<br />

and the slabs. Partial fixity may then be specified,<br />

and perhaps shear connections also provided. For<br />

high load on the roof or large spans, the composite<br />

action of a thin concrete slab on top of steel beams<br />

Downloaded from Digital Engineering Library @ McGraw-Hill (www.digitalengineeringlibrary.com)<br />

Copyright © 2004 The McGraw-Hill Companies. All rights reserved.<br />

Any use is subject to the Terms of Use as given at the website.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!