Component-wise time Extension & Anticipated Targets (Mile Stones) for D.P.R. under MH 3435 - GIA - NLCP Dal & Nageen Lake.<br />

Sl. No. Object Head Targets as<br />

per DPR<br />

Achievement<br />

ending<br />

March, 2011<br />

Balance/Residual<br />

project targets.<br />

Target date<br />

completion<br />

Physical Targets for the extension<br />

period.<br />

Year 2010 - 11 2011 - 12<br />

1 2 3 4 5 6 7 8<br />

1 Sewage Treatment works 100% 81.50% 18.50% March, 2012 9.50% 9.00%<br />

2 Solid waste management 100% 100.00% - March, 2012 - -<br />

3 Hydraulic works 100% 50.00% 50.00% March, 2012 28.00% 22.00%<br />

4 Restoration Dev. works 100% 63.00% 37.00% March, 2012 20.00% 17.00%<br />

5 Catchments management<br />

plan<br />

100% 31.20% 68.80% March 2012 35.00% 33.80%<br />

6 Infrastructure facilities 100% 15.00% 85.00% March, 2012 10.00% 75.00%<br />

7 Public awareness 100% 10.90% 89.10% March, 2012 10.00% 79.10%<br />

8 Unforeseen/Miscellaneous 100% 100.00% - March, 2012 - -<br />

9 Provision<br />

acquisition<br />

for land 100% 55.20% 44.80% March, 2012 25.00% 19.80%<br />

Annexure-G<br />

77