Component-wise time extension & fund requirement for D.P.R. under MH 3435 - GIA - NLCP Dal & Nageen Lake.<br />

Sl.<br />

No.<br />

Object Head Cost as per<br />

DPR.<br />

Rs. in lakhs<br />

Achievement<br />

ending<br />

March, 2011<br />

Balance/Residual<br />

project targets.<br />

Anticipated<br />

target date<br />

Funds requirement for extension<br />

period<br />

Year 2010 - 11 Year 2011 - 12<br />

1 2 3 4 5 6 7 8<br />

1 Sewage<br />

works<br />

Treatment 9691.68 5551.50 4140.18 March, 2012 2141.63 1998.55<br />

2 Solid waste 75.59 87.99 -12.40 March, 2010 (-)12.40 --<br />

3<br />

management<br />

Hydraulic works 1283.03 613.62 669.41 March, 2012 333.00 336.41<br />

4 Restoration<br />

works<br />

Dev. 4961.98 3006.22 1955.76 March, 2012 1580.00 375.76<br />

5 Catchments<br />

2584.00 1162.29 1421.71 March, 2012 737.40 684.31<br />

6<br />

management plan<br />

Infrastructure<br />

facilities<br />

1592.53 221.10 1371.43 March, 2012 171.32 1200.11<br />

7 Public awareness 541.08 59.65 481.43 March, 2012 50.00 431.43<br />

8 Unforeseen/Miscellan<br />

eous<br />

435.85 448.19 -12.34 March, 2012 (-)12.34 -<br />

9 Provision<br />

acquisition<br />

for land 8710.00 4811.35 3898.65 March, 2012 2000.00 1898.65<br />

Total 29875.74 15961.91 13913.83 - 6988.61 6925.22<br />