(ii) Financial<br />
Expenditure upto 3/94 Rs. 382.83 cr.<br />
Outlay <strong>1994</strong>-<strong>95</strong> Rs. 460.97 cr.<br />
Annual Expenditure/release Rs. 54.53 cr.<br />
<strong>1994</strong>-<strong>95</strong> upto 12/94<br />
Total Expenditure upto 12/94 Rs. 437.36 cr.<br />
(iii) Constraints<br />
Out <strong>of</strong> total 46 approved schemes, 21 are being<br />
partly funded by PFC / WB, 5 schemes are<br />
funded from their own resources. The progress<br />
<strong>of</strong> remaining 20 schemes pertaining to HSEB,<br />
UPSEB, BSEB, WBSEB, ASEB, DPL and<br />
DVC is however, very critical because <strong>of</strong><br />
paucity <strong>of</strong> funds.<br />
3.3 Renovation, Modernisation and Uprating <strong>of</strong><br />
Hydro-electric Power Stations<br />
(i) A programme for renovation, modernisation<br />
and uprating (RM&U) <strong>of</strong> Hydro Power<br />
Stations was formulated by Central Electricity<br />
Authority and presently 55 schemes have been<br />
identified under this programme with an<br />
aggregate capacity <strong>of</strong> 9658 MW. On a<br />
preliminary assessment, the programme would<br />
yield a benefit <strong>of</strong> 340 MW by way <strong>of</strong><br />
restoration <strong>of</strong> lost capacity; additional 519 MW<br />
capacity by way <strong>of</strong> uprating and 1337 MW as<br />
19<br />
prevention <strong>of</strong> capacity loss. The Restoration,<br />
Uprating and prevention <strong>of</strong> capacity loss efforts<br />
would yield 6709 million units <strong>of</strong> additional<br />
energy <strong>annual</strong>ly. The estimated cost <strong>of</strong> the<br />
programme is approximately Rs. 1260 crores.<br />
(ii) Out <strong>of</strong> 55 schemes, 32 schemes have already been<br />
cleared by CEA at an estimated cost <strong>of</strong> Rs. 652<br />
crores. The benefits expected after<br />
implementation <strong>of</strong> these Renovation schemes<br />
are 1548 MW and 4050 MU per annum. Out<br />
<strong>of</strong> these 32 schemes, 4 schemes have already<br />
been implemented and balance 28 schemes are<br />
under various stages <strong>of</strong> implementation. Total<br />
estimated cost <strong>of</strong> these 28 schemes is Rs. 635<br />
crores and the benefits expected after<br />
implementation <strong>of</strong> renovation works are 1476<br />
MW and 3679 MU per annum.<br />
(iii) The DPRs for 6 schemes are under processing/<br />
examination in CEA and the DPRs for the<br />
remaining 17 schemes are yet to be received<br />
from the Utilities/SEBs.<br />
(iv) During the year, Desk Review Clearance <strong>of</strong><br />
Sub-Station Equipments <strong>of</strong> Hirakud-(Burla)<br />
H.E. Power Station has been made at an<br />
estimated cost <strong>of</strong> Rs. 9.85 crores.<br />
The country’s largest training simulator at Korba.