06.08.2013 Views

The Alaska Contractor - Summer 2008

The Alaska Contractor - Summer 2008

The Alaska Contractor - Summer 2008

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Coeur hopes to<br />

begin production at<br />

Kensington gold mine<br />

in 2009<br />

BY PATRICIA LILES<br />

With completed underground mine workings and surface<br />

processing facilities, the Kensington mine northeast<br />

of Juneau should be producing about 150,000<br />

ounces of gold annually, employing about 200 people in the<br />

year-round operation.<br />

But instead, the recently constructed underground hardrock<br />

mine and surface processing facilities sit idle, even after<br />

the mine’s developer, Idaho-based Coeur d’Alene Mines<br />

has spent some $270 million to build the new operation.<br />

Problem is – the mine’s planned operation for disposal of<br />

tailings, which is the rock left over after gold is extracted, has<br />

to be changed to a process that will not only meet regulatory<br />

approval, but will pass muster with environmental groups<br />

that protested the project’s waste storage plan.<br />

Managers at Coeur <strong>Alaska</strong> had planned to store the leftover<br />

rock in the Lower Slate Lake, a 23-acre alpine lake. That<br />

process was included in Kensington’s plan of operation that<br />

concluded in 2005 with the approval of federal and state regulatory<br />

permits and the start of construction in mid-2005.<br />

Environmental groups argued against the tailing disposal<br />

plan and appealed the permits issued by regulatory agencies,<br />

a conflict that ultimately resulted in the wetlands permit for<br />

the tailings disposal plan to be suspended by federal regulators.<br />

<strong>The</strong> previously approved plan was argued thorough a<br />

variety of court proceedings, concluding with a March 2007<br />

ruling by the Ninth Circuit Court of Appeals that vacated the<br />

permits associated with the tailing facility.<br />

Meanwhile, construction crews working for Coeur continued<br />

on the underground mine workings and the surface<br />

processing plant and other related facilities. That work was<br />

concluded in August 2007, according to Coeur.<br />

In January <strong>2008</strong>, Coeur submitted a modified plan of operation<br />

to the U.S. Forest Service, the lead regulatory agency

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!