The Alaska Contractor - Summer 2008
The Alaska Contractor - Summer 2008
The Alaska Contractor - Summer 2008
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Coeur hopes to<br />
begin production at<br />
Kensington gold mine<br />
in 2009<br />
BY PATRICIA LILES<br />
With completed underground mine workings and surface<br />
processing facilities, the Kensington mine northeast<br />
of Juneau should be producing about 150,000<br />
ounces of gold annually, employing about 200 people in the<br />
year-round operation.<br />
But instead, the recently constructed underground hardrock<br />
mine and surface processing facilities sit idle, even after<br />
the mine’s developer, Idaho-based Coeur d’Alene Mines<br />
has spent some $270 million to build the new operation.<br />
Problem is – the mine’s planned operation for disposal of<br />
tailings, which is the rock left over after gold is extracted, has<br />
to be changed to a process that will not only meet regulatory<br />
approval, but will pass muster with environmental groups<br />
that protested the project’s waste storage plan.<br />
Managers at Coeur <strong>Alaska</strong> had planned to store the leftover<br />
rock in the Lower Slate Lake, a 23-acre alpine lake. That<br />
process was included in Kensington’s plan of operation that<br />
concluded in 2005 with the approval of federal and state regulatory<br />
permits and the start of construction in mid-2005.<br />
Environmental groups argued against the tailing disposal<br />
plan and appealed the permits issued by regulatory agencies,<br />
a conflict that ultimately resulted in the wetlands permit for<br />
the tailings disposal plan to be suspended by federal regulators.<br />
<strong>The</strong> previously approved plan was argued thorough a<br />
variety of court proceedings, concluding with a March 2007<br />
ruling by the Ninth Circuit Court of Appeals that vacated the<br />
permits associated with the tailing facility.<br />
Meanwhile, construction crews working for Coeur continued<br />
on the underground mine workings and the surface<br />
processing plant and other related facilities. That work was<br />
concluded in August 2007, according to Coeur.<br />
In January <strong>2008</strong>, Coeur submitted a modified plan of operation<br />
to the U.S. Forest Service, the lead regulatory agency