06.08.2013 Views

The Alaska Contractor - Summer 2008

The Alaska Contractor - Summer 2008

The Alaska Contractor - Summer 2008

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Historic Moody Tunnel<br />

he demolition this spring of the 262-foot-long historic<br />

Moody Railroad Tunnel, an 88-year-old landmark along<br />

the <strong>Alaska</strong> Railroad 600 feet north of the Nenana River<br />

Bridge, marked the end of an era. Moody Tunnel was built in<br />

the early 1920s during construction of the <strong>Alaska</strong> Railroad and<br />

was the last of two remaining tunnels north of Anchorage.<br />

<strong>The</strong> four-phase project included constructing the access<br />

road to the job site from the top of the George Parks Highway,<br />

blasting an equipment access road from the top of the tunnel<br />

site down to track level, removing the bedrock over the top of<br />

the tunnel, the tunnel demolition through schist bedrock, a<br />

safety realignment scheduled for October that will move the<br />

track off old timber cribbing, and the final clean up.<br />

Advanced Blasting Services, one of only a few technical<br />

explosives engineering contractors in <strong>Alaska</strong> and the company<br />

responsible for the demolition that now makes the railroad<br />

safer, says that technically the job was more challenging<br />

than the typical rock excavation project because the rock had<br />

to be excavated while preserving the tunnel’s structure so that<br />

it could still be in use while undergoing demolition.<br />

“That was the key,” said Mikel and Julia Saunders, owners<br />

of Advanced Blasting Services, explaining how they worked<br />

within scheduling windows between trains, maintaining<br />

traffic with only one track. “We had to be able to shoot one<br />

part while keeping the other part attached, safe and secure<br />

so trains could continue to run until the project was done.”<br />

Although the <strong>Alaska</strong> Railroad planned for a 36-hour shutdown,<br />

the longest downtime was 12 hours.<br />

demolished<br />

BY HEIDI BOHI<br />

<br />

<br />

<strong>The</strong> Moody Tunnel, which is eligible for listing on the<br />

National Register of Historic Places, is a federally assisted<br />

undertaking with funding through the Federal Transit Administration.<br />

By the time the project is complete, the <strong>Alaska</strong><br />

Railroad will have spent between $3.5 million and $4 million<br />

on the Moody Tunnel Demolition Project. <strong>The</strong> tunnel demolition<br />

was divided into three shots or “blasts.” A total of 9,000<br />

pounds of explosives, including 5,000 of dynamite and the<br />

rest blasting agents, were used resulting in 260 feet of tunnel<br />

collapsing into an estimated 4,000 cubic yards of rock, timber<br />

and debris. For the entire project, to date, 45,000 pounds of<br />

explosives have been used, including 10,000 pounds of dynamite,<br />

resulting in a total of 35,000 cubic yards of debris.<br />

Mikel Saunders said a lot of dynamite was required to<br />

assure complete collapse because if the tunnel shook, but<br />

did not completely come down, it would have been increasingly<br />

dangerous to re-shoot the unstable tunnel.<br />

<strong>The</strong> fourth and final phase of the demolition – safety realignment<br />

that moves material further back from the rail – will<br />

be completed this fall after passenger season ends in mid-September.<br />

An “open cut” remains where the tunnel once stood.<br />

Tunnels have always been a maintenance issue, said Regan<br />

Brudie, <strong>Alaska</strong> Railroad Project Engineer for the Moody Tunnel<br />

Demolition Project. But when the tunnel was first built in<br />

1921 it was the only solution for getting around the corner<br />

of Healy Canyon, which was a 10-degree curve through the<br />

tunnel. As trains have gotten bigger, load sizes were limited to<br />

what would fit through the Moody Tunnel. By removing the

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!