LEVEL<br />
Useful achievements<br />
Awareness of mobility<br />
service<br />
Degree of use of<br />
mobility service<br />
Satisfaction with the<br />
mobility service<br />
sumo – System for Evaluation of Mobility Projects<br />
Example of targets in the <strong>SUMO</strong> analysis levels<br />
for the Test Traveller project<br />
Acceptance of the offer<br />
Experimental individual<br />
behaviour<br />
Satisfaction with the<br />
offer<br />
Permanent individual<br />
behaviour<br />
System impact<br />
TARGETS<br />
Information campaigns to recruit test travellers have<br />
been carried out at at least four different companies<br />
in March.<br />
At least 80 per cent of persons at the company know<br />
about the project.<br />
At least 200 persons have participated in information<br />
meetings at the companies.<br />
At least 90 per cent of participants at meetings are<br />
satisfied with the information.<br />
At least 50 persons agree to become test travellers.<br />
At least 45 persons test public transport at least<br />
3 days per week for two months.<br />
At least 40 persons are satisfied with the tested<br />
public transport option.<br />
At least half of the test subjects (25 persons) continue<br />
to use public transport at least 3 times a week.<br />
Carbon dioxide emissions are reduced by at least<br />
20 tonnes per year.<br />
Figure 6.1 Example of targets in the <strong>SUMO</strong> analysis levels for the Test Traveller project