© Green Cat Renewables Ltd<br />
GLENLORA WIND TURBINE<br />
Figure 1.1.6 – Control, Metering and Protection Building<br />
1.2.10 Construction Programme<br />
The main construction period would last for approximately 3 to 5 months, from<br />
commencement of construction through reinstatement at the end of the construction<br />
period. Construction would consist of the following phases:<br />
Construction of site track for access to the turbine location including the excavation<br />
of cable trenches and the laying of electricity and communication cables.<br />
Construction of turbine foundations.<br />
The delivery and erection of turbine towers, nacelles and blades.<br />
Commissioning of the wind turbines.<br />
Site reinstatement.<br />
Measures to prevent contamination of the ground during the construction period<br />
would be implemented and continue throughout the life of the project. Including the<br />
following measures:<br />
Concrete: The foundation concrete specified would be of high strength structural<br />
grade which is not prone to leaching of alkalis.<br />
Page 22 of 173