© Green Cat Renewables Ltd<br />

GLENLORA WIND TURBINE<br />

Figure 1.1.6 – Control, Metering and Protection Building<br />

1.2.10 Construction Programme<br />

The main construction period would last for approximately 3 to 5 months, from<br />

commencement of construction through reinstatement at the end of the construction<br />

period. Construction would consist of the following phases:<br />

Construction of site track for access to the turbine location including the excavation<br />

of cable trenches and the laying of electricity and communication cables.<br />

Construction of turbine foundations.<br />

The delivery and erection of turbine towers, nacelles and blades.<br />

Commissioning of the wind turbines.<br />

Site reinstatement.<br />

Measures to prevent contamination of the ground during the construction period<br />

would be implemented and continue throughout the life of the project. Including the<br />

following measures:<br />

Concrete: The foundation concrete specified would be of high strength structural<br />

grade which is not prone to leaching of alkalis.<br />