4 Assessment of Effects<br />

4.1 Construction Effects<br />

4.1.0.1 Construction of the Scheme would primarily affect pedestrians and others<br />

using the footpaths and road network near to the works. However, during<br />

periods of traffic management, traffic may be diverted and cause temporary<br />

impacts to pedestrians and others using the road network further from the<br />

Scheme. Potential impacts on pedestrians and others would therefore have<br />

to be managed on a flexible basis during the construction period.<br />

4.1.0.2 During construction, access along the footpaths/cycleways within the<br />

vicinity of the Scheme would be maintained wherever possible. However,<br />

NMU may still be affected by construction activities, such as traffic<br />

management, operating construction vehicles, or the construction work<br />

itself. These impacts may include delays (e.g. waiting for construction<br />

vehicles to pass, longer routes), adverse conditions (i.e. possible mud on<br />

the footpath due to construction works) and potential increased sources of<br />

alarm to ridden horses (e.g. noise from construction vehicles).<br />

4.1.0.3 The sources of visual impacts on NMU during the construction period would<br />

result from the removal of existing vegetation and presence of earthworks,<br />

temporary lighting, signage, construction plant and machinery. There would<br />

be adverse visual impacts from footpaths directly affected by construction<br />

processes, and several footpaths in close proximity to the works would also<br />

suffer adverse visual impacts. NMU in the vicinity of structural works, in<br />

particular improvements at Tollbar End roundabout are likely to experience<br />

significant adverse visual effects associated with direct views to large<br />

machinery such as piling augers and other ancillary equipment.<br />

4.1.0.4 Footpath 443 currently links Rowley Road to the A45 Stonebridge Highway.<br />

During construction works, the footpath would be blocked for safety<br />

reasons, and would be permanently closed thereafter. Due to its current<br />

low usage, the consequential impact would be assessed as slight<br />

adverse, though it could be considered to be mitigated by a slightly longer<br />

walk around the land in question.<br />

4.1.0.5 The works to the Tollbar End roundabout would result in the modification of<br />

the pedestrian crossings and footpaths, cycleways and tracks in the area.<br />

Access across the roundabout would be maintained throughout the<br />

construction period and signage would be provided for NMU. These<br />

alternative accesses and crossings may result in slightly longer journey<br />

times. The resulting impact would be temporary slight adverse.<br />

4.1.0.6 A new footbridge over the River Sowe on the south side of the A45<br />

Stonebridge Highway, immediately east of Stivichall Junction, would be<br />

needed to allow the widening of the carriageway and re-routing of the<br />

existing combined footway and cycleway to avoid modifying the existing<br />

bridge. The separate footbridge specifically for the 3m wide combined<br />

cycleway / footway would be provided adjacent to and south of the existing<br />

River Sowe Bridge.<br />

Environmental Statement <strong>Volume</strong> 2<br />

A45/A46 Tollbar End Improvement<br />

Page 22<br />

<strong>Part</strong> <strong>12</strong>: Pedestrians et al<br />

March 2009