The HyTide 110-5.3 horizontal axis tidal turbine, a product of Voith Hydro with rated power of 110 kW and<br />

diameter of 5.3m, was installed in Jindo of Korea in the Spring of 2011. The site was used to test the turbine<br />

under extreme conditions. It has been tested for three months in <strong>2012</strong>, resulting in the availability of 94%<br />

and rotor power peak of 130 kW.<br />

Installation of HyTide 110-5.3 of Voith Hydro<br />

New Developments<br />

The Yongsoo wave power plant, a pilot plant of 500kW OWC (Oscillating Water Column) wave energy<br />

converter which has been developed by KIOST and funded by MLTM, is being constructed at Yongsoo, Jeju<br />

of Korea. However, its completion has been delayed for more than a year, mainly because of exceptionally<br />

frequent typhoons in the region during the summer period of <strong>2012</strong>. The construction of the caisson<br />

structure and underwater power cable will be finished in the second quarter of 2013. Then the installation<br />

of the generation equipment will be followed in the third quarter, expecting to start the test operation in<br />

late October 2013. A couple of turbines and generators of 250 kW capacity were manufactured in 2010<br />

and an integrated system of generator and power control module was extensively tested in the laboratory<br />

of Korea Electrotechnology Research Institute in 2011. A caisson structure of 15,000 tonnes has been<br />

constructed at a test site, which is 1 km off the coastline of Yongsoo in April <strong>2012</strong>. An underwater cable<br />

between the caisson structure and a power house on land is being deployed and it will be connected to<br />

the national grid later.<br />

Construction of Caisson Structure for Yongsoo Wave Power Plant<br />