21.01.2014 Views

OES Annual Report 2012 - Ocean Energy Systems

OES Annual Report 2012 - Ocean Energy Systems

OES Annual Report 2012 - Ocean Energy Systems

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

118<br />

As such Figure 1 is only an indicative cost trajectory based on particular assumptions of capacity factor and<br />

Opex expected for a wave energy technology. To describe acceptable cost constraints more generally, ESB<br />

has devised cost and performance envelopes.<br />

Phase 1 Cost & Performance Envelopes:<br />

Phase 1 projects will be required to establish the reliability and predictability of plant cost and performance<br />

in advance of larger project investments upon which economies of scale can be built. In order to understand<br />

the investment case in such activity, one must consider:<br />

1. The internal rate of return (IRR) demanded by a commercial investor: For such early projects, investors<br />

may be willing to accept a reduced IRR where there is strategic value to being involved in an early project,<br />

especially where it would provide access to subsequent investment opportunities. An IRR of 7% is selected<br />

for this analysis to determine realistic phase 1 project financing costs, though this will vary depending on<br />

the project and the investor appetite. An IRR of 7% is probably optimistic as it is not risk-adjusted to the<br />

uncertainty involved in the deployment of hardware in the marine environment without a proven track<br />

record of reliability. However, it is assumed that all safety critical risks can be managed satisfactorily at this<br />

stage.<br />

2. The revenue stream for the project: ESB considers that tariffs of circa €300/MWh are expected to be<br />

available in some jurisdictions (e.g. 5 ROCs in the UK market) to undertake these early projects of limited scale.<br />

3. The lifetime of the project: ESB considers that a reduced project economic life of 10-12 years is<br />

appropriate for Phase 1 projects as early technology is likely to become obsolete and be replaced at a date<br />

earlier than the design life.<br />

Based on the above, an affordable Capex per MW can be established. In order to represent technology<br />

variability, the affordable investment cost is presented in Table 1(a) and is calculated for varying capacity<br />

factor and annual Opex (as a percentage of Capex). Table 1(a) is the case where it is assumed that no<br />

additional grant aid is available for the project. This table provides an “affordable cost envelope” for private<br />

project financing of early stage projects.<br />

The influence of capacity factor and Opex on these affordable costs is considerable. For example, for a<br />

tidal stream generation plant rated at 1MW, a Capex in excess of €7m is affordable where capacity factors<br />

of 45% can be achieved but this reduces to only €4.75m where capacity factors are limited to 30% (for<br />

the case of Opex is 4% of Capex). Similar variation is apparent for wave energy technology, where there<br />

is ambiguity about how such converters are rated and consequently about what capacity factors can be<br />

expected. This highlights the need for caution in how developers rate energy conversion machines and for<br />

how investors compare the cost of technology using the crude metric of €/MW installed. There will also be<br />

variability in terms of Opex depending on reliability, accessibility and the cost of maintenance operations,<br />

such that the affordable investment costs can also vary considerably depending on these attributes. This<br />

highlights the need for project investors to undertake detailed technical due diligence to establish realistic<br />

expectations of energy production, reliability, availability and operational costs.<br />

Affordable Capex falls within the range of €3-8m for the range of capacity factors and Opex considered<br />

in Table 1(a). ESB anticipates that such early projects are more likely to fall in the range of €6-10m per<br />

MW. As such, it is likely there will be a shortfall between the required €6-10m and what can be justified<br />

as a commercial investment alone, especially where Opex is likely to be high and reliability low for phase<br />

1 projects. As such, these projects are termed “pre-commercial” by ESB and require additional sources of<br />

funding.<br />

Additional Phase 1 project funding:<br />

Grant aid is likely to be essential to establishing this vital bridging market of phase 1 ocean energy projects.<br />

Funding supports are already available through schemes such as the EU’s NER300 and the UK’s Marine<br />

ANNUAL<br />

REPORT <strong>2012</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!