<strong>Municipality</strong> <strong>of</strong> <strong>Lambton</strong> <strong>Shores</strong><br />

2012 Capital Expense Summary October 31, 2012<br />

PROJECT<br />

TOTAL 2012<br />

FINAL<br />

BUDGET<br />

2012<br />

EXPENSES<br />

TOTAL PROJECT<br />

EXPENSE<br />

COMMENTS<br />

Libraries<br />

Forest Library<br />

2-740-175-5100 Windows 12,692.85 544.71 544.71<br />

Old <strong>The</strong>dford Library<br />

2-740-175-5106 Council Chamber Renovations 26,443.43 2,293.04 2,293.04<br />

Portion <strong>of</strong> this budget was allocated to an emergency<br />

purchase <strong>of</strong> a furnace for the library. Remaining budget<br />

used to purchase the windows, and a partial installation will<br />

occur in 2012.<br />

Deferred to a medium term priority.<br />

Sound system to be purchased for TVC.<br />

Harbours<br />

GB Harbour<br />

2-350-350-5876 GB Harbour Alum Boat w/motor 4,855.01 4,443.32 4,443.32 Equipment Purchased<br />

2-350-350-5877 Lighting 5,288.69 226.97 226.97 Project concept currently being reconsidered<br />

2-350-350-5875 GB Harbour Security System 1,626.05 1,626.05 Funded from operating<br />

PF Harbour<br />

2-350-351-5880 Pavilion - ro<strong>of</strong> replacement 7,933.03 6,568.45 6,568.45 Complete<br />

2-350-351-5881 Accessibility 12,692.85 544.71 544.71<br />

Scope <strong>of</strong> work developed, solicitation <strong>of</strong> an electrical<br />

contractor pending<br />

2-350-351-5879 Northside Repair Launch 26,443.43 18,482.07 18,482.07 Complete - pending invoice<br />

Parks / Beaches<br />

Beach/Beach House<br />

2-710-716-5875 Fixtures 21,154.74 907.82 907.82 Countertops and sink fixtures to be completed in the fall.<br />

Eilber Park<br />

2-710-710-5883 Facility Upgrade (fixtures, countertop, ro<strong>of</strong>) 16,923.79 6,798.47 6,798.47 Completed<br />

Grand Bend Lions Park<br />

2-710-710-5101 Playground Equipment 30,000.00 23,420.12 25,793.33 complete<br />

2-710-710-5102 Infield Resurface 30,000.00 32,542.50 34,915.71 complete<br />

2-710-710-5103 Infield Fencing 35,000.00 30,917.34 34,081.60 complete<br />

2-710-710-5104 Accessibility 10,000.00 0.00 no funding received<br />

2-710-710-5106 Erosion Control 10,546.68 48,050.20 Carry forward from 2011<br />

Optimist Park<br />

2-710-710-5120 Play Equipment 12,000.00 9,720.94 10,907.54 Total expenses shown, 2011 expenses funded<br />

2-710-710-5121 Gazebo 7,000.00 10,291.24 23,695.43 Complete<br />

2-710-710-5122 Walkways / Plantings 16,000.00 14,321.83 15,903.95 Complete<br />

Klondyke Park<br />

2-710-710-5879 Irrigation System 10,623.17 490.14 490.14 Test well dug, work pending<br />

Other Bosanquet Parks<br />

2-710-710-5880 Land - Klondyke Rd Tree Farm 2,644.34 113.48 113.48<br />

This project has been cancelled due to concerns <strong>of</strong> ability to<br />

water trees once planted.<br />

Will be reconsidered if/when an irrigation system is installed.<br />

Utter Ball Diamond<br />

2-710-710-5882 Pavilion Ro<strong>of</strong> Replacement 11,635.11 11,342.87 11,342.87 Complete<br />

McRae<br />

2-710-710-5884 Backstop 6,346.42 2,564.27 2,564.27 Work completed internally<br />

Coultis<br />

2-710-710-5885 Washrooms 2,750.12 118.02 118.02 Complete - pending invoice<br />

Rotary Civic Square<br />

2-710-710-5886 Hydro Panel 3,702.08 158.87 158.87<br />

Currently developing specifications with a plan to size the<br />

panel to accommodate a possible future spray pad.<br />

Other Forest Parks<br />

2-710-710-5887 BMX Park 105,773.72 54,089.58 54,089.58 Asphalt pad laid, project completion by oct 31st, 2012<br />

<strong>The</strong>dford Village Green<br />

2-700-110-5103 Play Equipment 3,400.00 0.00 Complete - pending invoice, funding group.<br />

<strong>The</strong>dford Ball Diamond<br />

2-710-710-5888 Playground Equipment 19,039.27 7,178.47 7,178.47 Complete (project downsized)<br />

<strong>The</strong>dford Main St<br />

2-700-110-5101 Garbage Cans 2,000.00 1,874.94 1,874.94 Complete<br />

2-700-110-5107 Garbage and Cigarette Disposal Units 4,500.00 4,971.24 4,971.24 Complete<br />

2-700-110-5108 Trails - Benches & Signs 5,000.00 0.00 Request received from LSNT cttee, no direction <strong>of</strong> Council<br />

2-710-710-5881 Signage - Various Parks 5,288.69 226.97 721.39 Rendering pending<br />

2-700-110-5102 Community Signs 37,020.80 1,588.68 1,588.68<br />

1,073,901.57 488,000.70 560,257.93<br />

98<br />

page 3 <strong>of</strong> 4<br />

11/16/2012