PISD 2004 Bond Program<br />

Program Administrator: Jacobs<br />

Program Manager: Terry Page<br />

Phone: 713-740-0882<br />

Cell: 281-808-8550<br />

Executive Summary<br />

22. $39,058.00 from Facility Assessment Contingency to Turner ES.<br />

23. $600,000.00 from 2004 Bond Contingency Pool to Phillips Gym/Veterans Memorial Stadium.<br />

24. $4,556.00 from Facility Assessment Contingency to South Houston HS.<br />

25. $298,493.00 from 2004 Bond Contingency Pool to Dr. Dixie Melillo MS.<br />

26. $330,000.00 from 2004 Bond Contingency Pool to Transportation Center.<br />

27. $700,000.00 from 2004 Bond Contingency Pool to Keller MS.<br />

28. $1,586,500.00 from 2004 Bond Contingency Pool to South Belt ES.<br />

29. Savings of $4,916,000.00 from Various Campuses to 2004 Bond Contingency Pool.<br />

30. $3,400,000.00 from 2004 Bond Contingency Pool to Kruse ES.<br />

31. $233,385.00 from 2004 Bond Contingency Pool to Gardens ES.<br />

32. $16,615.00 from Facility Assessment Contingency to Gardens.<br />

33. $3,000,000.00 from 2004 Bond Contingency Pool to De Zavala MS.<br />

34. $1,200,000.00 from 2004 Bond Contingency Pool to De Zavala MS.<br />

35. $966,000.00 from 2004 Bond Contingency Pool to Land Acquisition.<br />

36. $23,434.00 from 2004 Bond Contingency Pool to Gardens ES.<br />

37. Savings of $3,924,579.00 from Various Campuses to 2004 Bond Contingency Pool.<br />

38. $100,000.00 from 2004 Bond Contingency Pool to Video Surveillance Cameras upgrades for various campuses.<br />

39. $24,725.00 from 2004 Bond Contingency Pool to Schneider MS for installation of additional HVAC monitoring devices.<br />

40. Savings of $2,523,465.00 from Various Campuses to 2004 Bond Contingency Pool.<br />

41. $5,925,000.00 from 2004 Bond Contingency Pool to Various 2004 Bond Pool funded projects (see BAI 03-31-09).<br />

Schedule:<br />

The <strong>Pasadena</strong> ISD 2004 Bond Program is currently on schedule. PISD 2004 Bond Program is scheduled for completion in October <strong>2009</strong>.<br />

Executive Summary<br />

Status Date: 10-<strong>May</strong>-<strong>2009</strong><br />

Page 9 of 45